Invoice # | Invoice Date | Due Date | Effective Date | Vendor Invoice# | Line # | Description | Total Amount | Override Net Amount | Invoice Status | Check # | Check Date |
167274 | 09/24/2014 | 10/28/2014 | 10/24/2014 | PR102214MH-6 | 1.00 | Tennis Facility at Rock Chalk Park - add electrical outlets for ball machines | 1,650.00 | false | Paid | 404,072.00 | 10/28/2014 |
167274 | 09/24/2014 | 10/28/2014 | 10/24/2014 | PR102214MH-6 | 2.00 | Tennis Facility at Rock Chalk Park - add pickleball striping on tow of the courts | 1,000.00 | false | Paid | 404,072.00 | 10/28/2014 |
167274 | 09/24/2014 | 10/28/2014 | 10/24/2014 | PR102214MH-6 | 3.00 | Tennis Facility at Rock Chalk Park - add water line for future drinking fountain | 3,500.00 | false | Paid | 404,072.00 | 10/28/2014 |
167141 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-5 | 1.00 | Sports Pavilion Lawrence - Change Order to provide Wall Patch to fill connector plate voids at the base of tilt-up wall panels. (proposed change order sheet #10 dated July 29th) | 4,620.00 | false | Paid | 404,072.00 | 10/28/2014 |
167141 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-5 | 2.00 | Sports Pavilion Lawrence - Change Order to provide painting of fire lines on the lower level. (Proposed change order sheet #11 dated July 29th) | 4,207.50 | false | Paid | 404,072.00 | 10/28/2014 |
167139 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-4 | 1.00 | Dehumidifying the Sports Pavilion Lawrence prior to
installation of wood flooring, as specified and approved by City Commission
7-1-14. Not to Exceed $12,350.00 |
12,350.00 | false | Paid | 404,072.00 | 10/28/2014 |
167137 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-3 | 1.00 | Sports Pavilion - Electrical
additions per City Request (change order sheet #12) 3 TV outlet on upper level $1600 Relocate test switch in concessions $150 Add power to divider wall $550 Add 4plex plugs on concourse poles $500 Add 8 outlets per side on courts 1 and 2 $9750 Add 1 TV outlet in each party room $625 Margin and overhead $1317.50 |
14,492.50 | false | Paid | 404,072.00 | 10/28/2014 |
167135 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-2 | 1.00 | Changes to the interior of the Sports Pavilion Lawrence (Item #1 - 7,000 sq ft Multi-purpose area) as specified and approved by City Commission 7-1-14 | 26,847.70 | false | Paid | 404,072.00 | 10/28/2014 |
167133 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-1 | 1.00 | Change order #1 at Sports Pavilion Lawrence. Approved by
City Commission 5-20-14 Add Concure Concrete mixt |
22,044.00 | false | Paid | 404,072.00 | 10/28/2014 |
167133 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-1 | 2.00 | Add electrical items as specified | 3,902.80 | false | Paid | 404,072.00 | 10/28/2014 |
167133 | 09/24/2014 | 10/28/2014 | 10/23/2014 | PR102214MH-1 | 3.00 | Add a mop sink in Storage (105 | 6,015.63 | false | Paid | 404,072.00 | 10/28/2014 |
166729 | 09/30/2014 | 10/28/2014 | 10/17/2014 | PR1227-11 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. | 971,233.81 | false | Paid | 404,072.00 | 10/28/2014 |
163685 | 08/31/2014 | 10/07/2014 | 10/01/2014 | PR1227-10 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay app #10 | 158,435.49 | false | Paid | 403,424.00 | 10/07/2014 |
160390 | 08/11/2014 | 09/02/2014 | 08/28/2014 | PR1227-9 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. | 599,396.40 | false | Paid | 402,506.00 | 09/02/2014 |
155627 | 06/30/2014 | 07/08/2014 | 07/03/2014 | PR1227-8 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. | 686,250.00 | false | Paid | 401,011.00 | 07/08/2014 |
153917 | 05/29/2014 | 06/24/2014 | 06/12/2014 | PR1227-07 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. pay app no. 7 | 1,027,209.60 | false | Paid | 400,696.00 | 06/24/2014 |
147722 | 03/31/2014 | 05/06/2014 | 04/28/2014 | PR1227-06 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay application #6 | 1,146,254.40 | false | Paid | 399,365.00 | 05/06/2014 |
144324 | 02/28/2014 | 03/25/2014 | 03/24/2014 | PR1227-05 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay application No. 5 | 1,107,934.20 | false | Paid | 398,309.00 | 03/25/2014 |
139892 | 12/31/2013 | 02/04/2014 | 02/03/2014 | PR1227-04 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay Application No. 4 | 1,643,622.30 | false | Paid | 397,161.00 | 02/04/2014 |
133664 | 10/31/2013 | 11/26/2013 | 11/25/2013 | PR1227-03 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay application #3 | 1,126,800.00 | false | Paid | 395,560.00 | 11/26/2013 |
130460 | 09/30/2013 | 10/22/2013 | 10/21/2013 | PR1227-02 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay app #2 | 1,530,474.30 | false | Paid | 394,787.00 | 10/22/2013 |
127578 | 08/31/2013 | 10/01/2013 | 09/27/2013 | PR1227-01 | 1.00 | Construction of Lawrence Recreation Center at Rock Chalk Park. Authorized by the City Commission on 5/21/2013. Total cost not to exceed $10,500,000. Pay app no. 1 | 452,389.50 | false | Paid | 393,819.00 | 10/01/2013 |
10,550,630.13 | |||||||||||
change orders not pursuant to the Recreation Center Construction Contract | 100,630.13 | ||||||||||
total without change orders | 10,450,000.00 |