Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss – City Manager Cynthia Wagner - Assistant City Manager Diane Stoddard - Assistant City Manager |
FROM: |
Philip Ciesielski – Assistant Utilities Director |
CC: |
Dave Wagner – Director of Utilities Mike Lawless –Utilities Deputy Director Beth Krishtalka – Assistant to Director Mark Hegeman – Utilities Operations Superintendent Dave King – Utilities Maintenance Superintendent |
Date: |
December 11, 2013 |
RE: |
Agenda Item – Award Bid for Bid Number B1359, Project UT1102KA Kaw WTP Raw Water Intake Replacement |
Please include the following item on the City Commission Agenda for consideration at the December 17, 2013 meeting:
Award the Bid for Bid Number B1359, Project UT1102KA Kaw WTP Raw Water Intake Replacement to the low bidder Wolf Construction in the amount of $3,800,000.00 and authorize the City Manager to execute the construction contract.
Project Description
The project provides for the construction of a redundant surface water intake and raw water pipeline to the Kaw Water Treatment Plant (WTP), and modifications to and dredging in the area of the active intake as recommended in the November 2012 Kaw Water Treatment Plant Raw Water Intake Evaluation by Black & Veatch. The construction of the new intake and raw water pipeline will provide a redundant point of raw water diversion from the Kansas River for the Kaw WTP. These facilities will also serve as the first phase of Kansas River raw water supply required for the potential expansion of the Kaw WTP to a treatment capacity of 25 MGD. The modifications to the existing intake involve raising the top to above the new water surface as impounded by Bowersock Dam, installing a sediment shield on the intake pipe to reduce the intake of sand into the pipe and Low Service Pump Station No.2, and dredging in the immediate area of the intake. Additionally the two (2) abandoned intakes and piping will be removed. See the attached map indicating the location of the work.
Project History
January 24, 2012 - City Commission authorized execution of the Engineering Services Agreement for the work.
September 5, 2012 - Received draft report.
September 20, 2012 - Provided Staff review comments to Black & Veatch.
November 20, 2012 - Received updated report.
December 18, 2012 – City Commission authorized execution of Supplemental Agreement for the design of immediate modifications to the existing intake structure and dredging of accumulated river bed material in the vicinity of the intake. These improvements are currently being designed and permitted with dredging expected to take place this summer and construction of the modifications during fall and winter.
March 12, 2013 – City Commission authorized Staff to negotiate a Supplemental Agreement with Black & Veatch for engineering services related to the construction of a new intake and raw water piping.
May 7, 2013 – City Commission authorized the execution of a Supplemental Agreement with Black & Veatch for engineering and construction phase services for the project.
October 1, 2013 – Staff provided an update on the status of the project on the City Manager’s Report.
October 22, 2013 - City Commission set a bid date of November 19, 2013.
November 5, 2013 – Staff and representatives from Black & Veatch conducted a prebid meeting for interested contractors.
Project Status
On November 19, 2013, bids were received from the following three (3) bidders. The bids were opened and publicly read aloud.
Wolf Construction |
$3,800,000.00 |
LG Barcus |
$3,880,000.00 |
Kissick Construction |
$6,193,550.00 |
|
|
Engineer’s Estimate |
$4,702,000.00 |
Black and Veatch has reviewed the bids, financial status and qualifications of the Wolf Construction and, per the attached letter, recommend awarding the bid to the low bidder Wolf Construction.
Project Schedule |
Days From Notice to Proceed |
City Commission Set a Bid Date |
October 22, 2013 |
Prebid Meeting |
November 5, 2013 |
Bid Opening |
November 19, 2013 |
Award Bid |
December 17, 2013 |
Milestone 1 New Intake Complete |
May 15, 2014 |
Substantial Completion |
June 15, 2014 |
Final Completion |
July 1, 2014 |
Project Funding
The project is included in the Department of Utilities 2013 Capital Improvements and Rate Plan and is identified in the proposed Bond Funds per Resolution 7019.
Action Request:
Award the Bid for Bid Number B1359, Project UT1102KA Kaw WTP Raw Water Intake Replacement to the low bidder Wolf Construction in the amount of $3,800,000.00 and authorize the City Manager to execute the construction contract.
Thank you for your assistance. Please advise if you have any questions.