Memorandum
City of Lawrence
Public Works
TO: |
David L. Corliss |
FROM: |
Chuck Soules |
CC: |
Diane Stoddard, Cynthia Wagner, Jonathan Douglass |
Date: |
April 26, 2012 |
RE: |
South Lawrence Trafficway |
PROJECT HISTORY:
The South Lawrence Trafficway (SLT) has had a long and eventful history. Following is a brief summary of that history:
1964 |
First proposal of the SLT |
1966 |
DOT Act |
1968 |
Civil Rights Act |
1969 |
National Environmental Policy Act |
1975 |
Clinton Lake finished |
1986 |
FHWA gets involved with SLT / publishes Notice of Intent to prepare Environmental Impact Study (EIS) |
1990 |
FHWA complete EIS 31st Street Alignment selected |
1991 |
Final design began |
1993 |
Construction on west leg of SLT begins |
1994-2002 |
Multiple alignments / potential designs for a 31st Street, 32nd Street, 35th Street and 38th Street evaluated |
2002 |
Final EIS for eastern portion of SLT recommends 32nd Street “B” Alignment |
2003 |
Record of Decision(ROD) issued by Corps of Engineers |
2008 |
|
2009 |
First 142 acres of wetland mitigation completed |
2010 |
Field Check KDOT and FHWA win lawsuit |
2011 |
Lawsuit appended KDOT begins final design |
On June 3, 2011, KDOT announced the T-Works Program which is a 10 year, $8 billion transportation program. Among projects to be completed is the eastern leg of the SLT. The project is estimated to cost $188 million. The SLT project had the highest regional economic impact of all the projects in Kansas, estimated at $3.428 billion.
|
|
2012 |
Legal arguments heard in January |
2013 |
Tentative letting is scheduled for Fall 2013 pending appeal decision |
PROJECT SPECIFICS:
Road Improvements (FIGURE 1)
|
|
|
|
|
|
|
|
|
Wetlands and Mitigation (FIGURE 3)
|
Mitigation 317.0 acres Net additional wetlands provided 259.4 acres |
|
|
|
|
|
|
31st Street, Haskell to O’Connell Road (FIGURE 1)
|
|
City / State Agreement (ATTACHMENT 1)
The City Commission is asked to approve the agreement between the City and State for several items: |
1) The agreement allows KDOT to perform appraisal and property acquisition for the City’s portion of 31st Street from Haskell Avenue to O’Connell Road and use the earmark the City received for property acquisition costs. The earmark will not cover all costs and the City will have to fund the remainder, 2) allows KDOT to bid and construct the 31st Street project for the City, 3) City will reimburse KDOT for construction cost per the payment schedule in article II, paragraph 14, 4) states that KDOT will prepare plans, bid and build the K-10 project, 5) since several local streets are affected the agreement authorizes KDOT to complete the project within City limits and use City owned property (existing right-of-way), 6) the City will maintain the pedestrian facilities constructed, 7) give the City back 23rd Street from Iowa to East Hills Drive pending agreement between the City and State on any maintenance work needed, 8) City will maintain certain bridges constructed on local streets within the City limits, 9) City will vacate the existing 31st Street right-of-way adjacent to Haskell University to be given back to the university, 10) City will maintain the lighting, 11) State will deed to the City the property south of Mary’s Lake for a park/wildlife area, 12) City agrees to a certain stormwater design for drainage purposes, 13) City is contributing $150,000 of Surface Transportation funds to the completion of the multi-use path between Iowa and Louisiana. |
ACTION REQUESTED: Pending City Commission discussion:
· Adopt Resolution No. 6969, authorizing the Mayor to execute Agreement No. 12-12 with KDOT for the construction of improvements to K-10 (SLT) and the construction of 31st Street from Haskell Avenue to O’Connell Road. |