| CITY OF LAWRENCE | |||||||||||
| Project No. 11-SR4-306(C) | |||||||||||
| 2006 Overlay Program, Phase 2 | |||||||||||
| BID TAB | |||||||||||
| Engineer's Estimate: $1,490,820.75 | |||||||||||
| R. D. Johnson Excavating Co. | Kansas Heavy Construction, LLC | LRM Industries, Inc. | Miller Paving & Construction, LLC | ||||||||
| ITEM | DESCRIPTION | UNITS | QUANTITY | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT | UNIT PRICE | AMOUNT |
| 1 | Milling (2") | SY | 45,964 | $ 1.80 | $ 82,735.20 | $ 1.80 | $ 82,735.20 | $ 1.75 | $ 80,437.00 | $ 2.00 | $ 91,928.00 |
| 2 | Asphaltic Concrete Overlay (2") (BM-2) | TONS | 3,293 | $ 43.00 | $ 141,599.00 | $ 43.25 | $ 142,422.25 | $ 43.85 | $ 144,398.05 | $ 50.43 | $ 166,065.99 |
| 3 | Asphaltic Concrete Overlay (2") (BM-2 Special) | TONS | 2,017 | $ 46.00 | $ 92,782.00 | $ 46.00 | $ 92,782.00 | $ 47.50 | $ 95,807.50 | $ 54.63 | $ 110,188.71 |
| 4 | Asphaltic Concrete Pavement Patch (full depth) (BM-2)* | TONS | 313 | $ 90.00 | $ 28,170.00 | $ 90.00 | $ 28,170.00 | $ 105.00 | $ 32,865.00 | $ 120.75 | $ 37,794.75 |
| 5 | Concrete Pavement Patch (full depth)* | SY | 2,106 | $ 70.00 | $ 147,420.00 | $ 52.80 | $ 111,196.80 | $ 78.65 | $ 165,636.90 | $ 98.50 | $ 207,441.00 |
| 6 | 6" Concrete Pavement (Reinforced) | SY | 1,689 | $ 50.15 | $ 84,703.35 | $ 45.85 | $ 77,440.65 | $ 46.40 | $ 78,369.60 | $ 52.65 | $ 88,925.85 |
| 7 | 30" Concrete Curb & Gutter (8" toe) | LF | 2,681 | $ 19.10 | $ 51,207.10 | $ 19.70 | $ 52,815.70 | $ 22.20 | $ 59,518.20 | $ 28.75 | $ 77,078.75 |
| 8 | 24" Concrete Curb & Gutter (8" toe) | LF | 24,856 | $ 16.85 | $ 418,823.60 | $ 18.00 | $ 447,408.00 | $ 18.30 | $ 454,864.80 | $ 23.50 | $ 584,116.00 |
| 9 | 24" Concrete Curb & Gutter (8" toe)(Laydown) | LF | 2,134 | $ 17.35 | $ 37,024.90 | $ 19.50 | $ 41,613.00 | $ 18.30 | $ 39,052.20 | $ 22.75 | $ 48,548.50 |
| 10 | 4" Concrete Sidewalk | SY | 783 | $ 35.20 | $ 27,561.60 | $ 33.20 | $ 25,995.60 | $ 37.45 | $ 29,323.35 | $ 55.35 | $ 43,339.05 |
| 11 | 6" Concrete Access Ramp | EACH | 2 | $ 1,000.00 | $ 2,000.00 | $ 1,000.00 | $ 2,000.00 | $ 1,200.00 | $ 2,400.00 | $ 1,875.00 | $ 3,750.00 |
| 12 | 6'x4' Curb Inlet | EACH | 6 | $ 3,650.00 | $ 21,900.00 | $ 3,900.00 | $ 23,400.00 | $ 3,700.00 | $ 22,200.00 | $ 4,850.00 | $ 29,100.00 |
| 13 | 6'x4' Curb Inlet Lid (Retrofit) | EACH | 1 | $ 1,300.00 | $ 1,300.00 | $ 1,200.00 | $ 1,200.00 | $ 1,875.00 | $ 1,875.00 | $ 6,150.00 | $ 6,150.00 |
| 14 | Abandon Existing Curb Inlet | EACH | 2 | $ 1,500.00 | $ 3,000.00 | $ 1,200.00 | $ 2,400.00 | $ 1,600.00 | $ 3,200.00 | $ 3,800.00 | $ 7,600.00 |
| 15 | Asphaltic Concrete Edge Patch | SF | 863 | $ 2.35 | $ 2,028.05 | $ 2.70 | $ 2,330.10 | $ 3.25 | $ 2,804.75 | $ 3.75 | $ 3,236.25 |
| 16 | Crackfilling * | LF | 35,235 | $ 0.55 | $ 19,379.25 | $ 0.55 | $ 19,379.25 | $ 0.60 | $ 21,141.00 | $ 0.70 | $ 24,664.50 |
| 17 | Pavement Crack/Joint Membrane * | LF | 37,715 | $ 1.50 | $ 56,572.50 | $ 1.50 | $ 56,572.50 | $ 1.55 | $ 58,458.25 | $ 1.80 | $ 67,887.00 |
| 18 | Manhole Adjustment | EACH | 10 | $ 800.00 | $ 8,000.00 | $ 625.00 | $ 6,250.00 | $ 660.00 | $ 6,600.00 | $ 1,275.00 | $ 12,750.00 |
| 19 | Valve Adjustment | EACH | 8 | $ 220.00 | $ 1,760.00 | $ 180.00 | $ 1,440.00 | $ 190.00 | $ 1,520.00 | $ 925.00 | $ 7,400.00 |
| 20 | Water Meter Adjustment | EACH | 3 | $ 220.00 | $ 660.00 | $ 245.00 | $ 735.00 | $ 200.00 | $ 600.00 | $ 1,125.00 | $ 3,375.00 |
| 21 | Cold Plastic Reflectorized Pavement Marking | $ - | $ - | $ - | |||||||
| a) 24" Solid White Stop Line (class A) | LF | 64 | $ 14.70 | $ 940.80 | $ 14.00 | $ 896.00 | $ 15.65 | $ 1,001.60 | $ 18.20 | $ 1,164.80 | |
| b) 36" Solid White Crosswalk Line (class A) | LF | 168 | $ 18.90 | $ 3,175.20 | $ 18.00 | $ 3,024.00 | $ 19.00 | $ 3,192.00 | $ 23.40 | $ 3,931.20 | |
| c) 6" Dotted White Lane Line (class A) | LF | 10 | $ 4.20 | $ 42.00 | $ 4.00 | $ 40.00 | $ 4.20 | $ 42.00 | $ 5.20 | $ 52.00 | |
| d) 6" Broken White Lane Line (class A) | LF | 1,630 | $ 4.20 | $ 6,846.00 | $ 4.00 | $ 6,520.00 | $ 4.20 | $ 6,846.00 | $ 5.20 | $ 8,476.00 | |
| e) 6" Solid White Channelization Line (class A) | LF | 716 | $ 4.20 | $ 3,007.20 | $ 4.00 | $ 2,864.00 | $ 4.20 | $ 3,007.20 | $ 5.20 | $ 3,723.20 | |
| f) Left Turn Lane - Use Arrow | EACH | 10 | $ 315.00 | $ 3,150.00 | $ 300.00 | $ 3,000.00 | $ 315.00 | $ 3,150.00 | $ 400.00 | $ 4,000.00 | |
| g) 6" Broken Yellow Lane Line (class B) | LF | 1,070 | $ 4.45 | $ 4,761.50 | $ 4.25 | $ 4,547.50 | $ 4.50 | $ 4,815.00 | $ 5.60 | $ 5,992.00 | |
| h) 4" Solid Double Yellow Lane Line (class B)** | LF | 200 | $ 5.25 | $ 1,050.00 | $ 5.00 | $ 1,000.00 | $ 5.25 | $ 1,050.00 | $ 6.50 | $ 1,300.00 | |
| 22 | Traffic Signal Loops | LF | 336 | $ 11.00 | $ 3,696.00 | $ 12.00 | $ 4,032.00 | $ 11.35 | $ 3,813.60 | $ 22.25 | $ 7,476.00 |
| 23 | Temporary Surfacing* | TONS | 50 | $ 20.00 | $ 1,000.00 | $ 20.00 | $ 1,000.00 | $ 24.50 | $ 1,225.00 | $ 125.00 | $ 6,250.00 |
| 24 | Traffic Control | LS | 1 | $ 35,000.00 | $ 35,000.00 | $ 48,440.45 | $ 48,440.45 | $ 29,385.00 | $ 29,385.00 | $ 36,000.00 | $ 36,000.00 |
| 25 | Seed, Fertilize, & Mulch | LS | 1 | $ 14,835.00 | $ 14,835.00 | $ 15,950.00 | $ 15,950.00 | $15,300.00 | $ 15,300.00 | $ 6,500.00 | $ 6,500.00 |
| GRAND TOTAL | $ 1,306,130.25 | $ 1,309,600.00 | $ 1,373,899.00 | $ 1,706,204.55 | |||||||