Wakarusa Water Reclamation Facility

Overview | Community Involvement | FAQ | Contact US | Links

Monthly Progress Report 07-03-07


Completed Tasks through June 30, 2007

  • Continued dialog with Kansas Department Health and Environment (KDHE) regarding review of the Siting Study. 
  • Draft NPDES Permit Public Notice Period ended June 16. City received draft permit from KDHE.
  • Continued to support City in annexation, zoning, and platting of Wakarusa WRF site.
  • Completed remaining on-site corridor investigations (geotechnical and utility locates).
  • Provided City with draft corridor on-site investigation reports including: cultural and historic evaluation, wetlands delineation and threatened endangered species investigation, Phase 1 Environmental assessment, geotechnical borings, and assessment of existing road conditions.
  • Held workshop with City to discuss operating strategies of biological nutrient removal process.
  • Presented preliminary treatment layouts for Design Memorandum.

Anticipated Tasks for July 2007

  • Finalize Siting Study based on comments received from City Commission, City Staff, and KDHE. Re-submit final Siting Study.
  • Continue to support City in annexation, zoning, and platting of Wakarusa WRF site.
  • Submit Corridor Study which will include alignments considered and results of on-site investigations.
  • Present preliminary solids layouts for Design Memorandum to City for comments.
  • Submit draft Design Memorandum to the City for comments.
  • Initiate geotechnical borings for detailed design on the Wakarusa WRF site.
  • Update Basis of Design Report as comments are received from City and KDHE.

Actions/Issues

  • Important to maintain project timeline.
  • Work with County to define truck route.
  • Design/build team selected for West Influent Pumping Station should provide further definition of station location.
  • Communicate conveyance corridor route selection information to property acquisition team and design/build team.

Decisions Needed

  • Continue to evaluate project acceleration plan.
  • Response from KDHE on review of Siting Study.