Monthly Progress Report 02-26-07


Completed Tasks through February 2007

  • Proposed corridor and site flown for aerial survey.
  • Met with staff and property acquisition team to select proposed pipeline corridor.
  • Disinfection, odor control, hydraulic analysis, and benefits memorandums forwarded to staff for review.
  • Preliminary treatment, odor control, and disinfection preliminary results were discussed with the staff.
  • Completing draft Basis of Design Report, pending completion of sampling program for Volatile Fatty Acids (VFA).
  • Continue dialog with Kansas Department Health and Environment regarding review of the Siting Study.  Prepared draft Wakarusa River modeling report.
  • Supported City in acquisition of property.
  • Worked on annexation and zoning request for WRF site.

Tasks for March 2007

  • Determine proposed pumping station (PS-50) location south of the Wakarusa. Update strip maps of possible piping corridor to the Wakarusa WRF utilizing data from the aerial survey. 
  • Commence discussions with property owners along proposed corridor route and pumping station location.
  • Submit Draft Basis of Design Report to staff for review following availability of VFA sampling data.
  • Begin development of Process and Instrumentation Diagrams.
  • Finalize Siting Study based on Comments received from City Commission, City Staff, and KDHE.  Re-Submit Siting Study to Owner as required.
  • Continue to support City in acquisition of property.
  • Submit planning submittal for annexation of Wakarusa WRF Site.
  • Meet with City and KDHE to discuss results of Wakarusa River modeling report.

Actions/Issues

  • Important to maintain project timeline.

Decisions Needed

  • Continue to evaluate project acceleration plan.
  • Evaluate need to perform water quality monitoring on the Wakarusa River.
  • Response from KDHE on review of siting study.
  • Continue to evaluate project acceleration plan.
  • Response from KDHE on review of Siting Study.