Completed Tasks through April 24, 2007
- Continued dialog with Kansas Department Health and Environment regarding review of the Siting Study.
- Provided KDHE with updated Wakarusa River modeling report. Public notice for NPDES permit expected in late April.
- Submitted zoning, annexation, and preliminary plat information. Topic scheduled for May Planning Commission agenda.
- Held meeting to update Public Advisory Subcommittee Representatives on project status on April 11, 2007.
- Held Public Meeting No. 5 on April 23, 2007 to present proposed corridor alignment to the public.
- Design flows and solids handling memorandums reviewed with staff.
- Initiated on-site investigations of proposed piping corridor. Continued coordination and access discussions with property owners along proposed corridor route and pumping station locations.
- Continued progress on preliminary hydraulic profile and mass balance for the Wakarusa WRF.
Anticipated Tasks for May 2007
- Finalize Siting Study based on Comments received from City Commission, City Staff, and KDHE. Re-submit final Siting Study.
- Support City in annexation, zoning, and platting of Wakarusa WRF site for May Planning Commission Meeting.
- Submit Draft Basis of Design Report to staff for review.
- Begin development of Process and Instrumentation Diagrams as well as the Design Memorandum.
Actions/Issues
- Important to maintain project timeline.
- Monitor public comments on draft NPDES permit.
Decisions Needed
- Continue to evaluate project acceleration plan.
- Response from KDHE on review of Siting Study.