Tech Resources

  • See Technical Specifications, Design Criteria and Standard Details for the planning and construction process on the Technical Resources page.

Wakarusa Water Reclamation Facility

Overview | Community Involvement | FAQ | Contact Us | Links

PAC Meeting Agenda
October 26th, 2005

(City) Introductions & Today's Agenda  10 min

(PBA) PAC Roles & Responsibilities  10min

  • Provide your input as interested public stakeholders
  • Represent your group's interests
  • Conduit for public input
  • Provide balance of wants/needs
  • Respect others input
  • Respect the confidentiality of the process

(B&V) Wastewater 101  15 min

  • General wastewater treatment review
  • Wastewater treatment plant vs. water reclamation facility
  • Review role of the collection system
  • Typical concerns
    • Odor
    • Aesthetics
    • Noise
    • Lighting
    • Truck traffic
    • Residuals disposal

(B&V/PBA) Project Overview  20min

Need for Wakarusa Water Reclamation Facility (B&V)

  • Horizon 2020/Land use plan
  • Master Plan Recommendations
  • Growth Rate is Exceeding Population Projections
  • Timeline

Requirements and considerations (B&V/HNTB)

  • No preconceived locations
  • Accommodate gravity flow to the extent possible
  • Existing constraints
    • Existing collection system
    • Wetlands
    • Cultural & historic locations
  • Engineering issues (B&V/HNTB/B&W)
    • Can not build in floodway
    • Floodplain considerations
    • Environmental permitting
    • Site geology
    • Site topography
    • Proximity to utilities
    • Proximity to roadways
    • Affordable w/in rate plan

(B&V/PBA) Introduction to Process  15 min

  • Public input into criteria for selection (B&V/PBA)
    • Public acceptability factors
    • Site utilization/Compatability with land use
    • Appearance
  • Stakeholder Public Advisory Committee (PAC) (PBA)
    • Engaged with project team throughout the process
    • May be requested to stay with team through 2011
  • Stakeholder Interviews
    • Currently being schedules/conducted
  • Peer Group Roles (B&V)
    • Peer group qualifications
  • Process timeline (B&V)

(PBA) Solicit Input  20 min

  • Open discussion of process and improvement potential.