Annual Budget
PROGRAM IMPROVEMENT DECISION PACKAGE
Fund Department Division Dept Rank City Rank[1]
001 1070 557 1  
         
TYPE OF PROGRAM ADJUSTMENT
DESCRIPTION OF PROGRAM      
   
DATA PROTECTION PROJECT  
This project would involve installing a data storage RAID at the City's Wastewater 
Treatment Plant to better protect the City's servers.  A backup of each server 
would be instantly maintained at the 'bit' level, allowing any update of a database to
automatically be updated at the remote site.  This project would allow the City's email
server, Court server, GIS server, Imaging server, Active Directory server and shared
Citydata' server to have the data duplicated to a secure remote site to be maintained by
Information Systems.  The server replication process would be handled by NSI's 
"Double-Take" server replication and recovery option software.  The Email server would
be setup as a fail-over server that could immediately take over if the primary server had
a problem.  The other servers would replicate their server's data to a storage server
to prevent data loss.  
         
BENEFITS OF FUNDING PROGRAM      
   
These are critical servers for the daily operations of the City of Lawrence and represent
many thousands of employee hours in maintenance.  This project would insure that critical
data would always have an immediate backup available in case of a hardware malfunction
on a critical server or loss of a building.  
       
ESTIMATE AND EXPLANATION OF NEW REVENUE    
   
None  
         
CONSEQUENCES OF NOT FUNDING PROGRAM    
   
Critical data would be less protected and more at risk of loss or corruption.  
The cost of this project far outways the value of the data represented on these servers.
       
POSITIONS INVOLVED IN PROGRAM IMPROVEMENT    
   
Network Administrator, Information Systems Department.  
         
FINANCING OF PROGRAM
FIRST YEAR SECOND YEAR THIRD YEAR
PERSONAL SERVICES      
CONTRACTUAL SERVICES  $              2,000    
COMMODITIES    $            24,948  $              4,455  $              4,455
CAPITAL OUTLAY    $              9,500    
TOTAL COST    $            36,448  $              4,455  $              4,455
SAVINGS FROM FUNDING PKG.  
NET COST    $            36,448
ANNUAL COST (IF DIFFERENT FROM NET)  $            36,448
Annual Budget
PROGRAM IMPROVEMENT DECISION PACKAGE
PERSONAL SERVICES
10-01 Regular Salaries    
10-02 Overtime    
10-04 Longevity Pay    
10-04 Holiday Pay    
10-06 Parttime Salaries    
12-01 FICA    
12-02 Unemployment    
12-03 KPERS    
12-06 Life Insurance    
     
Subtotal    $                   -  
CONTRACTUAL SERVICES
Integration Costs    $              2,000
     
     
     
     
Subtotal    $              2,000
COMMODITIES
SERVER LICENSES:    
Email Server    $              2,772
Email Fail-over    $              2,772
Court Server    $              2,772
GIS Server    $              2,772
Imaging Server    $              2,772
CityData Server    $              2,772
Active Dir Server    $              2,772
Storage Server 1    $              2,772
Storage Server 2    $              2,772
     
Subtotal    $            24,948
CAPITAL OUTLAY
Storage RAID    $              9,500
     
     
     
     
Subtotal    $              9,500
TOTAL      $           36,448

[1]
Roderick L. Bremby:

This cell should be left blank.