Criteria Possible Scores
0 1 2
consistency with community goals and plans project is inconsistent with City's Comprehensive Plan or does nothing to advance the City Commission's strategic goals project is consistent the City's Comprehensive Plan but does little to advance the City Commission's strategic goals project are directly consistent with the City's Comprehensive Plan and advances the strategic goals of the City Commission
public health and safety project would have no impact on existing public health and/or safety status project would increase public health and/or safety but is not an urgent, continual need or hazard project addresses an immediate, continual safety hazard or public health and/or safety need
Mandates or other legal requirements project is not mandated or otherwise required by court order, judgment, or interlocal agreements project would address anticipated mandates, other legal requirements, or interlocal agreements project required by federal, state, or local mandates, grants, court orders and judgments; required as part of interlocal agreements
maintains or improves standard of service project not related to maintaining an existing standard of service project would maintain existing standard of service project would address deficiencies or problems with existing services; would establish new service
extent of benefit projects would benefit only a small percentage of citizens or particular neighborhood or area project would benefit a large percentage of citizens or many neighborhoods or areas project would benefit all of the citizens, neighborhoods, or areas
related to other projects project is not related to other projects in the Capital Improvement Plan already underway project linked to other projects in the Capital Improvement Plan already underway but not essential to their completion project essential to the success of other projects identified in Capital Improvement Plan already underway
public perception of need project has no public support or established voter appeal; is not identified by the citizenry as a need  project has been identified by the citizenry as a need in the community but lacks strong support project has technical and strong political support, project was suggested by or even demanded by large number of citizens
efficiency of service project would have no impact on the efficiency of service project would result in savings by eliminating obsolete or inefficient facilities project would result in significant savings  by increasing the efficiency of the performance of a service or reducing the on-going cost of a service or facility
supports economic development project would discourage or directly prevent capital investment, decrease the tax base, decrease valuation, or decrease job opportunities project would have no impact on capital investment, the tax base, valuation, or job opportunities project would directly result in capital investment, increased tax base, increased valuation, or improved job opportunities
environmental quality project would have a negative effect on the environmental quality of the city project would not effect the environmental quality of the city project would improve the sustainability of the environment
feasibility of project project is unable to proceed due to obstacles (land acquisition, easements, approval required) minor obstacles exist, project is not entirely ready to proceed  project is entirely ready to proceed, no obstacles (land acquisition or easements, approvals required, etc.) exist
opportunity cost if deferred, the increase in project costs would be less  than the rate of inflation if deferred, the increase in project costs would be equal to inflation  if deferred, the increase in project costs would be greater than the rate of inflation
operational budget impact project would significantly increase debt service, installment payments, personnel or other operating costs or decrease revenues project would neither increase or decrease debt service, installment payment, personnel or other operating costs or revenues project would decrease debt service, installment payments, personnel or other operating costs or increase revenues