Memorandum
City of Lawrence
Utilities Department
TO: |
Diane Stoddard – Interim City Manager Casey Toomay – Assistant City Manager |
FROM: |
Beth Krishtalka – Assistant to Utilities Director |
CC: |
Mike Lawless – Utilities Deputy Utilities Bob Brower – Superintendent Scott Fewins – Utilities Manager Sean Sloan – Purchasing Officer |
DATE: |
September 25, 2015 |
RE: |
Approve UT1510 Change Order to Purchase Order #013418 for Emergency Waterline Repairs at 23rd and Massachusetts |
Background
On August 24, 2015, staff was notified of a water leak at 23rd and Massachusetts Streets requiring immediate attention and repair, including replacement of 12 feet of waterline as well as asphalt pavement removal and approximately 120 feet of asphalt pavement replacement for three lanes of 23rd Street.
An original emergency purchase order was issued to R.D. Johnson for $14,000 prior to knowing the full extent of the repairs that would be needed at the site.
Project Status
The contractor’s site activities are now complete, with services totaling $42,287.72. These services include extensive traffic control in managing high traffic proximate to the work site. In accordance with the City’s Purchasing Procedures, we request Commission approval of the change order needed to increase emergency Purchase Order #013418 by $28,287.70 for a new Purchase Order total of $42,287.72.
Project Funding
Purchase is funded from the Utilities Non-Bonded Cash Construction.
Action
Approve change order to emergency purchase order #013418 to R.D. Johnson in the amount of $28,287.70 for a new total of $42,287.72 for emergency waterline repairs at 23rd and Massachusetts.