Memorandum
City of Lawrence
Utilities Department
TO: |
Diane Stoddard – Interim City Manager Casey Toomay – Assistant City Manager |
FROM: |
Beth Krishtalka – Assistant to Utilities Director |
CC: |
Mike Lawless – Utilities Deputy Utilities Dave King – Superintendent Steve Rich – Utilities Manager Sean Sloan – Purchasing Officer |
DATE: |
September 10, 2015 |
RE: |
Variable Frequency Drive for Wastewater Pump Station 5B Pump #1 |
Background
Pump Station 5B receives wastewater from a large portion of the collections system and pumps it to the Kaw River Wastewater Treatment Plant. Pump functionality is critical during high flows and rain events.
Recent Event
A recent lightning strike has operationally compromised Pump Station 5B’s pump #1 and its related variable frequency drive (VFD). Staff has determined the damaged VFD is not repairable, with replacement required for pumping reliability. Staff has negotiated a quote of $61,505.00 for the VFD, startup services, and five-year warranty from Logic, Inc., the local supplier for the Department’s specified standard VFDs from manufacturer ABB.
Concurrently, damaged pump #1 is under evaluation for possible repair by manufacturer Douglas Pump. Following evaluation, depending on the cost, staff will follow up as appropriate for Commission consideration.
Project Funding
Purchase will be funded from the Utilities Operations and Maintenance Budget.
Action
Authorize the sole-source purchase of one ABB Variable Frequency Drive from Logic, Inc. for $61,505.00 for the Kaw Wastewater Treatment Plant Pump Station 5B pump #1.