Memorandum
City of Lawrence
Public Works Department
TO: |
David Cronin, P.E., City Engineer |
FROM: |
Nicholas Voss, P.E., Project Engineer |
CC: |
Mark Thiel, Assistant Director of Public Works Charles F. Soules, P.E., Director of Public Works |
DATE: |
April 21, 2015 |
RE: |
Project PW 1521 - Lighting for 31st and O'Connell Intersection - set bid date of May 19, 2015 |
Background
The intersection of 31st and O'Connell has been constructed as part of the South Lawrence Trafficway. Lighting for this intersection was not included in the original plans.
Project Description
This project consists of installing street lighting to the roundabout at the intersection of 31st Street and O'Connell Road. Four black decorative street light poles with LED fixtures will be placed in the island inside of the roundabout.
Project Funding
This project will be funded with bonds issued for the construction of 31st Street, Resolution No. 7047. The estimated cost of the project is $40,000.
Project Schedule
This project will begin in June, 2015. Pole manufacture and delivery can take up to 8 to 12 weeks. The project should be completed by August, 2015.
Action Request
Set a bid date of May 19, 2015 for PW1521, Lighting for 31st and O'Connell Intersection.