Memorandum

City of Lawrence

Finance Department

 

TO:

Dave Corliss, City Manager

FROM:

Bryan Kidney, Finance Director

DATE:

April 1, 2015

RE:

Review bids received and approve sale of $90,680,000* water and sewage system improvement revenue bonds, series 2015 bonds to the lowest responsible bidder.  Consider declaring an emergency and adopt on first and second reading, Ordinance No. 9102, authorizing and providing for the issuance of water and sewage bonds, series 2015. Consider adopting Resolution No.7111 prescribing the forms and details of and authorizing and directing the sale and delivery of water and sewage system improvement revenue bonds, series 2015.

 

Background

The City of Lawrence currently has outstanding a $59,900,000 general obligation temporary note that matures May 1, 2015. The note was issued to finance a variety of water and wastewater projects. The projects funded by the note are either substantially complete or are anticipated to be completed within the next 18-24 months. The City needs to definitively fund the projects with long-term financing.

 

In addition to the projects currently financed with the temporary note, the Utilities Department has identified additional water and wastewater projects that need financing for 2015. We identified a portion of the 2015 projects that have defined costs and will be included in the 2015 permanent bond issue instead of issuing temporary financing. We should be able to lower issuance costs and lock into a lower interest rate due to higher investor in one large bond issue. We plan to consider financing for the remaining 2015 projects in the fall of 2015 as the project costs become more defined.

 

Projects

Projects included in the 2014 temporary note are:

 

Project Description

Amount

Kaw WTP Improvements - raw water intake

4,779,809

Oread Storage Replacement and Booster Pump Station

3,960,131

Kaw Transmission Main

7,851,831

Water Tower Maintenance and Pump Station Improvements

2,078,581

Watermain Assessment, Relocation, Rehabilitation, Replacement

9,895,531

Kaw WTP Improvements

1,537,925

Wakarusa WWTP - Influent Pump Station and Force Mains

21,709,727

Inflow & Infiltration Reduction

4,292,982

Sanitary Sewer Rehabilitation

1,851,731

Pump Station 4 and Force Main Improvements

1,142,922

Clinton Intake

1,455,354

Clinton Taste & Odor Process

1,549,748

Sanitary Sewer Relocations and Plant Imp.

728,728

Less: Premium on Note sale

-2,935,000

Total

$59,900,000

 

These projects were all authorized before the temporary notes were issued.

 

Portion of new projects for 2015 to be financed with Revenue Bond:

 

Project Description

Amount

Wakarusa 2015 plant improvements

$21,685,000

Watermain Assessment, Relocation, Rehabilitation, Replacement

4,096,900

Sewer Rehabilitation, Assessment, CIPP, Manholes, Relocation, and Replacement

949,900

     Total

$26,731,800

 

The Wakarusa project has been previously authorized by the City Commission. The new water and sewer rehab projects were approved by the City Commission on March 10.

 

In addition to funding the project costs, we estimate that there will be the additional financing costs and reoffering premium for a total estimated bond issue size of $90,680,000* calculated as follows:

 

 

Use of Funds

Amount

2014 temporary note projects

$59,900,000

2015 projects

26,731,800

Accrued interest on 2014 temporary note

1,497,500

Debt Service Reserve Fund

5,762,690*

Cost of Issuance

1,089,104*

Less: estimated premium

(4,301,094)*

     Total estimated bond size

$90,680,000*

 

The bonds will be 25 years with level annual debt service starting with an interest only payment in November 2015 and the first principal payment in 2016. The total cost of the projects and debt service for the bonds are under the amounts that were used in the latest rate model update.

 

Bond Sale

The City will conduct a competitive bond sale at 11:00 AM on Tuesday, April 7. Staff will bring to the Commission at the April 7 Commission meeting a completed bond ordinance and resolution to accept best bid and authorize issuance of the bonds.

 

The sale is not complete until an ordinance is adopted naming the purchaser of the bonds. An ordinance does not go into effect until a second reading. Staff is requesting the Commission declare an emergency and adopt the ordinance on first and second readings on the night of the sale.

 

Action Requested

The City Commission is requested to review bids received and approve the issuance and delivery of $90,680,000* water and sewage system improvement revenue bonds, series 2015 bonds to the best bidder. Consider declaring an emergency and adopt on first and second reading, Ordinance No. 9102, authorizing and providing for the issuance of water and sewage bonds, series 2015. Consider adopting Resolution No. 7111, prescribing the forms and details of and authorizing and directing the sale and delivery of water and sewage system improvement revenue bonds, series 2015.

 

*Amounts subject to change based on bids received on day of sale.