chuck's calculation Warren
Cap            22,500,000       22,500,000       22,500,000                    -  
Rec Center           (10,500,000)      (10,550,630)      (10,450,000)             50,630
architect               (925,000)          (941,408)          (901,018)             16,408 capped per development agreement at $925k
land               (784,050)          (784,333)          (784,050)                  283 includes actual closing costs
change orders                161,654           161,654           161,654                    -  
assist foundation              1,000,000         1,000,000         1,000,000                    -  
subtotal avail for infra            11,452,604       11,385,283       11,526,586             67,321
subtotal payments           (10,359,633)      (10,359,633)      (10,359,633)                    (0)
remaining owed to developer              1,092,971         1,025,650         1,166,953             67,321
to be paid by Assists Foundation              1,000,000         1,000,000                    -  
to be paid by City                  92,971             25,650             67,321