Memorandum

City of Lawrence

Utilities Department

 

TO:

David L. Corliss – City Manager

Diane Stoddard – Assistant City Manager

Casey Toomay – Assistant City Manager

Brandon McGuire – Assistant to the City Manager

FROM:

Andy Ensz – Project Engineer

CC:

Dave Wagner – Director of Utilities

Mike Lawless – Deputy Director of Utilities

Philip Ciesielski – Asst. Director of Utilities

Beth Krishtalka – Assistant to Director

Bob Brower – Utilities Operations Superintendent

DATE:

February 18, 2015

RE:

Execute Change Order No. 2 for Project UT1314, Lawrence Avenue Waterline Replacement increasing the contract amount by $18,282.00

 

Background/Project Description

The Lawrence Avenue waterline replacement project, as shown on the attached map, includes the replacement of the existing 1978 12” ductile iron waterline from 31st Street to 27th Street. The project includes the installation of approximately 2,960 lineal feet of 12” PVC waterline utilizing horizontal directional drilling as the primary installation method to minimize pavement removal and replacement and disturbance of existing surface features. The project will be completed in a single phase and is planned to be completed within 210 calendar days from the date that notice to proceed is issued.

 

Project History

The Lawrence Avenue waterline replacement project was evaluated as part of a preliminary design report, which established viable alternatives for alignment, project prioritization, construction cost estimates, and sequencing that will align with planned street rehabilitation work and budgeted funding. The assessment study identified the Lawrence Avenue waterline as the fifth priority for replacement due to the frequency of main breaks. The first three priority projects, 23rd Street (Iowa to Louisiana), North Iowa Street (Riverridge to Lakeview), and Mississippi Street from 3rd to 9th Streets, have been completed. The fourth priority project, Ellis Drive from 19th Street to Engel Road, is being coordinated with the University of Kansas as part of the redevelopment of the Daisy Hill and Stouffer Place housing facilities and is expected to be completed in several phases.

 

Project Details

Change Order No. 2 represents a net increase to the construction contract of $18,282.00 with no change to the contract times. Change Order No. 2 includes costs to connect the existing 4” fire line to First Free Methodist Church of Lawrence directly to the new 12” waterline on the east side of Lawrence Ave. that was installed as part of this project. This will isolate the fire line from the existing 6” waterline on West 30th Ct. Professional Engineering Consultants and Staff have reviewed the proposed Change Order No. 2 and recommend authorizing its execution.

 

Construction Contract Costs


Original Contract

Change Order No. 1

Change Order No. 2

Current Contract Total

$581,785.00

$11,190.00

$18,282.00

$611,257.00


 

Change order cost adjustments are 5.1% of the original contract amount.

 

Project Funding

The project is funded from the Department of Utilities bonded construction fund per the adopted Capital Improvement Project Scenario 5 for the 2013-2017 period.

 

Action

Authorize the City Manager to execute Change Order No. 2 to the existing construction contract with Schuetz Const, LLC for Project UT1314, Lawrence Avenue Waterline Replacement increasing the contract amount by $18,282.00.