Memorandum

City of Lawrence

Utilities Department

 

TO:

David L. Corliss – City Manager

Diane Stoddard - Assistant City Manager

Casey Toomay – Assistant City Manager

FROM:

Melinda Harger – Utilities Engineer

CC:

Dave Wagner – Director of Utilities

Mike Lawless – Deputy Director of Utilities

Philip Ciesielski – Assistant Director of Utilities

Beth Krishtalka – Assistant to Director

Mark Hegeman – Utilities Operations Superintendent

Dave King – Utilities Maintenance Superintendent

Leah Morris – Project Engineer

DATE:

February 5, 2015

RE:

Reset Bid Date for Project UT1304 Contract 4 Wakarusa Wastewater Treatment Plant and Conveyance Corridor

 

Project Status

At the January 13, 2015 City Commission meeting, the City Commission set a bid date of February 17, 2015 for Project UT1304 Contract 4 Wakarusa Wastewater Treatment Plant and Conveyance Corridor.  Due to the complexity of this project, bidders have requested a bid date extension. The Department of Utilities recommends extending the bid opening one week to February 24, 2015 in order to allow sufficient time for bidders to put together quality bid packages.

 

Action

Reset bid date of February 17, 2015 to February 24, 2015 for Bid Number B1467, Project UT1304 Contract 4 Wakarusa Wastewater Treatment Plant and Conveyance Corridor.