Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss – City Manager Diane Stoddard - Assistant City Manager Casey Toomay – Assistant City Manager |
FROM: |
Melinda Harger – Utilities Engineer |
CC: |
Dave Wagner – Director of Utilities Mike Lawless – Deputy Director of Utilities Philip Ciesielski – Assistant Director of Utilities Beth Krishtalka – Assistant to Director Mark Hegeman – Utilities Operations Superintendent Dave King – Utilities Maintenance Superintendent Leah Morris – Project Engineer |
DATE: |
February 5, 2015 |
RE: |
Reset Bid Date for Project UT1304 Contract 4 Wakarusa Wastewater Treatment Plant and Conveyance Corridor |
Project Status
At the January 13, 2015 City Commission meeting, the City Commission set a bid date of February 17, 2015 for Project UT1304 Contract 4 Wakarusa Wastewater Treatment Plant and Conveyance Corridor. Due to the complexity of this project, bidders have requested a bid date extension. The Department of Utilities recommends extending the bid opening one week to February 24, 2015 in order to allow sufficient time for bidders to put together quality bid packages.
Action
Reset bid date of February 17, 2015 to February 24, 2015 for Bid Number B1467, Project UT1304 Contract 4 Wakarusa Wastewater Treatment Plant and Conveyance Corridor.