Memorandum

City of Lawrence

Parks & Recreation Department

 

TO:

David Corliss, City Manager

CC:

Toni Wheeler, City Attorney

Ernie Shaw, Interim Director, Parks & Recreation

FROM:

Mark Hecker, Assistant Director, Parks and Recreation

DATE:

November 13, 2014

RE:

Sports Pavilion Lawrence – Construction Change Orders

 

Below are the change orders that were processed for the Sports Pavilion Lawrence facility as it was being constructed. All of these items are things that we requested outside of the contract agreement. All have been paid using a separate purchase order.

 

Project Description

Change Order #1 - Concure for track concrete, mop sink, electric outlets

$31,962

CC Approved 5/20/14

Sales Tax Reserve

Change order  #2 for multi-purpose room wall, concessions wall  header, floor blocking on gym floor #1 and #2

$26,847

CC Approved 7/1/14

Sales Tax Reserve

Dehumidification of building - split cost with contractor

$12,350

CC Approved 7/1/14

Sales Tax Reserve

Change Order #3 for electrical upgrades for TV's and added outlets

$14,492

CC Approved 7/8/14

Sales Tax Reserve

Change Order #4 in-fill wall connector plates on concrete walls and painting sprinkler pipes on lower level

$8,828

Sales Tax Reserve

Change order to add electric, water and pickleball to tennis courts

$6,150

CC Approved 6/24/14

Sales Tax Reserve

Sales Tax Reserve for Change Orders at SPL  - Sub Total

$100,629