Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss City Manager Diane Stoddard Assistant City Manager Casey Toomay Assistant City Manager |
FROM: |
Andy Ensz Utilities Project Engineer |
CC:
DATE: |
Dave Wagner Director of Utilities Mike Lawless Deputy Director of Utilities Philip Ciesielski Asst. Director of Utilities Beth Krishtalka Assistant to Director Bob Brower Utilities Operations Superintendent Brandon McGuire Assistant to the City Manager September 30, 2014 |
RE: |
October 7, 2014 Agenda Item Award the construction contract for Bid No. B1433 to Westland Construction, Inc. in the amount of $396,889.00 and authorize the City Manager to execute the construction contract for Project No. UT1312 Bob Billings Parkway Waterline Replacement. |
Background
The Bob Billings Parkway waterline replacement project was evaluated as part of a preliminary design report, which established viable alternatives for alignment, project prioritization, construction cost estimates, and sequencing that will align with planned street rehabilitation work and budgeted funding. The assessment study identified the Bob Billings Parkway waterline as the initial project to be included in the 2014-2015 program. The existing 1997 12 ductile iron waterline has experienced numerous failures due to the highly corrosive soils present in this area coupled with the fact that the watermain was installed without protective measures against corrosion.
Project Description
The Bob Billings Parkway waterline replacement project, as shown on the attached map, includes the replacement of the existing 1997 12 ductile iron waterline from George Williams Way to Bobwhite Drive. The project includes the installation of approximately 2,100 linear feet of 12 PVC waterline utilizing horizontal directional drilling as the primary installation method to minimize pavement removal and replacement, and disturbance of existing surface features. The project will be completed in a single phase and is planned to be completed within 120 calendar days from the date that notice to proceed is issued.
Project Details
Professional Engineering Consultants completed construction documents for the project and it was advertised for bid on September 2, 2014. Bids were opened on September 23, 2014 and the bids listed below read publicly aloud.
Westland Construction, Inc. |
$396,889.00 |
Schuetz Construction, LLC |
$621,812.00 |
NPL Construction Co., Inc. |
$629,134.00 |
Nowak Construction Co., Inc. |
$848,143.00 |
Engineers Estimate |
$455,570.00 |
Professional Engineering Consultants have reviewed the bids, qualifications, and current project commitments of the low bidder, Westland Construction, Inc., and, per the attached letter and bid tabulation, recommend awarding the bid to Westland Construction, Inc.
Project Funding
The project is funded from the Department of Utilities bonded construction fund per the adopted Capital Improvement Project Scenario 5 for the 2013-2017 period.
Action
Award the construction contract for Bid No. B1433 to Westland Construction, Inc. in the amount of $396,889.00 and authorize the City Manager to execute the construction contract for Project No. UT1312 Bob Billings Parkway Waterline Replacement.