Memorandum

City of Lawrence

Utilities Department

 

TO:

David L. Corliss – City Manager

Diane Stoddard – Assistant City Manager

Casey Toomay – Assistant City Manager

Brandon McGuire – Assistant to the City Manager

FROM:

Leah Morris – Project Engineer

CC:

Dave Wagner – Director of Utilities

Mike Lawless – Deputy Director of Utilities

Philip Ciesielski – Assistant Director of Utilities

Beth Krishtalka – Assistant to the Director

Bob Brower – Utilities Operations Superintendent

DATE:

August 13th, 2014

RE:

Agenda Item – Project UT1205, Contract 1 - South Lawrence Trafficway 24” Sanitary Sewer Relocation, Approve Request For Change #024 and #025

 

Background

The South Lawrence Trafficway is currently under construction by Emery Sapp & Sons (ESS) the general contractor for the Kansas Department of Transportation.

 

Required watermain and sanitary sewer relocations in the area of 31st and Haskell were designed and bid as part of the KDOT SLT project due to the required construction sequencing in this area. The construction of these relocations will be paid for by the City of Lawrence.

 

The sanitary sewer and watermain relocations in the area of 31st and Louisiana have been included into the KDOT Project No. K-8392-04 South Lawrence Trafficway plans by the execution of the City – State Supplemental Agreement No. 1.  City Commission approved the execution of the City – State Supplemental Agreement No. 1 with KDOT during the March 25th, 2014 City Commission meeting. The construction of these relocations will be paid for by the City.

 

Project Status

RFC #024

In the process of construction of the relocated 24” gravity sanitary sewer located southwest of 31st and Louisiana (see attached map), it was discovered during installation that a pallet of 24” pipe had a different transition between the bell and the pipe.  This pallet of slightly different pipe was supplied from a different production facility, and 19 joints of this pipe were installed.  While this pipe does meet specifications and performance measures, the Utility Department prefers that the pipe within the project be uniform.  The rest of the pallet that wasn’t installed was replaced with the pipe from the original production facility. 

The installed sewer has been pressure tested and inspected with CCTV to confirm that there are no performance or maintenance issues throughout these 19 joints of pipe.

 

ESS has offered a credit for the 266 linear feet (19 joints) of 24” diameter pipe for the installed pipe that came from the different production facility in the amount of $11,158.70 (see attached letter from ESS).

 

RFC#025

In the process of construction of the relocated 24” gravity sanitary sewer located southwest of 31st and Louisiana (see attached map), an unforeseen geotechnical condition was encountered.  During the excavation for the sewer, a perched water table was encountered near the flow line of the proposed sewer.  This perched water table changed the soil conditions enough that the typical means and methods of sewer installation weren’t possible.  The method of installation that is acceptable to stabilize the pipe in these conditions includes removing 5-7 feet of unsuitable material and replacing it with a bed of graded shot rock then followed by the City’s standard pipe embedment material. 

 

Per City Commission approval on May 20th, 2014 RFC #014 was issued to cover the additional costs of adding this stabilization on the initial 2,500 of the 3,203 linear feet of sanitary sewer.  According to the geotechnical information available, it was anticipated that beyond the initial 2,500 linear feet of sanitary sewer installed, this perched water table would recede.  However, continued construction of the remaining 24” sanitary sewer, as well as investigation of the 10” sanitary sewer, found similar soil conditions. 

 

The bed of graded shot rock is averaging 6 feet deep and 6-7 feet wide and consists of rocks as large as 24” in diameter being placed at the bottom.  This process is described in the attached letter from ESS.  The installed sewer is being monitored daily by Utilities inspection staff as well as weekly by Utilities Department staff by CCTV and survey to ensure that the installed pipe has no deflections.  Utilities staff have observed the construction methods and feels that this process is the best installation alternative for the sewer. 

 

Emery Sapp is requesting additional costs to continue this work on the remaining sanitary sewer.  As outlined in the attached letter from ESS, they have provided a unit cost of $72.58 per cubic yard of the additional shot rock placed, which includes the additional labor and material.  It is estimated that this method of stabilization will be necessary for remaining 741 of the 3,203 linear feet of 24” sanitary sewer as well as the 397 linear feet of the 10” sanitary sewer being constructed, as well as stabilization around the manholes.  Based on Note 6 within the Contract 1 plan set, which states “The Contractor shall provide a stable foundation at the base of the sanitary sewer excavation.  Over excavation and placement of additional crushed stone and/or over excavation and placement of lean concrete seal is anticipated, this work is at the contractor’s expense”, Emery Sapp will be responsible for the first 1.5’ of depth stabilization within the trench and it is requested that the City be responsible for the remaining depth.  Measurements are being recorded daily to track the actual volume of rock placed.  At the estimate of 6 feet deep and 6-7 feet wide, the total cost for 741 linear feet of 24” pipe and 397 linear feet of 10” pipe will amount to a cost of $91,559.67.  These quantities include subgrade stabilization around the sanitary manholes.

 

Construction Contract Costs:

Original Contract 1 - 24” Sanitary Sewer Relocation

   $710,069.63

Original Contract 2 – Inverted Sanitary Siphon and Waterline

$1,212,298.10

RFC #014

   $181,450.00

RFC #021

$8,613.16

RFC #024

-$11,158.70

RFC #025

$91,559.67

Current Contract Total

 $2,192,831.86

 

To date cost adjustments are 14.1% of the original contract amount.

 

Action

Authorize the City Manager to execute RFC # 024 and #025 to the construction contract with Emery Sapp & Sons for project UT1205 – Contract 1, South Lawrence Trafficway Sanitary Sewer Relocations increasing the contract amount by $80,400.97.

 

Thank you for your assistance.  Please advise if you have any questions.