Background
In order to fund a $3 million complete street re-build of 9th Street between Massachusetts and Delaware, the City will need to debt finance a substantial portion of the project and use infrastructure sales tax proceeds as well. Staff recommends that the plan to re-build Queens Road north of 6th Street be delayed and that funding for major maintenance and traffic calming/control work on Bob Billings Parkway be reduced.