Memorandum
City of Lawrence
Utilities Department
TO: |
David L. Corliss City Manager Cynthia Wagner - Assistant City Manager Diane Stoddard - Assistant City Manager |
FROM: |
Melinda Harger Utilities Engineer |
CC: |
Dave Wagner Director of Utilities Mike Lawless Deputy Director of Utilities Philip Ciesielski Assistant Director of Utilities Beth Krishtalka Assistant to Director Mark Hegeman Utilities Operations Superintendent Dave King Utilities Maintenance Superintendent |
Date: |
April 14, 2014 |
RE: |
Agenda Item Execute a Supplement to the Existing Engineering Services Agreement for Project UT1304 Wakarusa Wastewater Treatment Plant and Conveyance Corridor Facilities |
Background/Project Description
The 2012 Wastewater Utilities Master Plan and Capital Improvements Program recommend the construction of the Wakarusa Wastewater Treatment Plant (WWTP) and Conveyance Corridor facilities to be online in 2018. These improvements are required to mitigate wet weather surcharging of sanitary sewers along the 31st Street Corridor, provide for relief of wet weather overloading at the existing WWTP, and provide additional organic treatment capacity to provide for future growth of the community.
Previous Master Planning (2003), preliminary engineering, regulatory approvals, and land acquisitions by the City (2006-2007) provided property for the new WWTP. However, the preliminary efforts to locate a new pumping station to serve the proposed Wakarusa WWTP at that time were canceled due to an overall cessation of the project due to global economic issues. During the time period between 2007 and 2012, extensive efforts were completed by the City to reassess all aspects of the proposed system, and a new location for the pump station at the northwest corner of 31st and Louisiana Streets was identified as an optimal location for its intended purpose. This location will allow Pump Station No. 10 (PS No. 10) to provide for wastewater flow transfer to the new Wakarusa WWTP and to provide flow relief to the existing Haskell Pump Stations 5A and 5B.
The Wakarusa WWTP will use Biological Nutrient Removal (BNR) to remove nitrogen and phosphorous in addition to other traditional treatment requirements. This higher level of treatment is required by the new discharge permit for the Wakarusa WWTP and will allow the City to improve its environmental stewardship at this facility compared to the existing WWTP. The new Wakarusa WWTP will supplement and support the existing Kansas River WWTP, which currently provides treatment to the entire City. PS No. 10 will be designed to allow the two WWTPs to work together as a single system to provide operational flexibility and redundancy. These new facilities will allow the City to meet the current and future growth needs throughout the City service areas, and will improve the overall operational capabilities of the City to manage its wastewater system in a more cost-efficient manner.
Project Status
March 12, 2013 City Commission authorized staff to advertise a Request for Proposals for Engineering Services for the Wakarusa Wastewater Treatment Plant and Conveyance Corridor Facilities.
July 23, 2013 City Commission authorized execution of the engineering services agreement with Black & Veatch Corporation for Phase 100/150 in the amount of $299,000. Phase 100/150 for initial project design services included data acquisition, concept review, alternate force main evaluation, SLT coordination, regulatory review, and platting for the pump station and treatment plant sites. Services provided by Black & Veatch in partnership with PEC and Bartlett & West.
October 22, 2013 City Commission authorized execution of Supplement No. 1 with Black & Veatch in the amount of $1,566,900. This supplemental agreement included [Phase 200] preliminary design for the Wakarusa WWTP and Pump Station No. 10 as well as [Phase 300/350] final design of the force mains, roads adjacent to the WWTP, and WWTP site fill. Services provided by Black & Veatch in partnership with PEC, Bartlett & West, and Treanor.
December 16, 2013 Planning Commission voted to approve the preliminary plat for the Wakarusa Wastewater Treatment Plant Addition.
December 18, 2013 Planning Commission voted to approve the rezoning and preliminary plat for Pump Station No. 10.
January 7, 2014 City Commission authorized execution of an agreement with Baker University for easements related to the Wakarusa Wastewater Treatment Plant and Conveyance Corridor Facilities.
March 4, 2014 City Commission acknowledged the final plat for Pump Station No. 10.
March 11, 2014 City Commission accepted dedication and vacation of easements and rights-of-way associated with the final plat for the Wakarusa Wastewater Treatment Plant Addition.
March 11, 2014 City Commission set a bid date of April 1, 2014 for Project UT1304 Contract 1 Wakarusa Conveyance, Haskell Avenue Casing Pipe.
March 24, 2014 City Manager executed Supplement No. 2 with Black & Veatch in the amount of $14,645. This supplemental agreement adds a facility space needs analysis to the scope of work. Services provided by Black & Veatch in partnership with Treanor.
April 8, 2014 City Commission awarded UT1304 Contract 1 Wakarusa Conveyance, Haskell Avenue Casing Pipe to Emery Sapp & Sons, Inc. in the amount of $88,600.
April 8, 2014 City Commission authorized execution of Supplement No. 3 with Black & Veatch in the amount of $71,983. This supplemental agreement included additional preliminary design tasks and detailed design of the Baker Wetlands enhancements. Services provided by Black & Veatch in partnership with PEC and Bartlett & West.
Project Details
A Basis of Design Report has been completed by Black & Veatch in partnership with PEC, Bartlett & West, and Treanor Architects. The detailed report and preliminary drawings included design criteria, conceptual site layouts, 3D (BIM) modeling for structures, process and instrumentation diagrams of major systems, equipment lists, code and permitting requirements, implementation schedules, and a preliminary opinion of probable construction costs. The Basis of Design Report satisfies the objective to establish agreement on scope, parameters, performance requirements, and project approach for the final design.
As stated in the Basis of Design Report, the Wakarusa WWTP design includes two treatment trains, which provides the City an opportunity to select a capacity for the plant after receiving bids. The design will include a 2.5 million gallons per day (MGD) single-train treatment facility in the base bid and a larger 5.0 MGD dual-train treatment facility as a bid alternate. The Report also identifies future expansions at the WWTP to accommodate growth within the City for years to come. This vision of expansion will be considered in the current design to provide the City with cost effective options for future expansions as needed. The project will include the construction of the following structures and facilities:
Utility Department Staff has reviewed the Basis of Design report and is pleased with the proposed design concepts and treatment process. Based on this report, Staff has negotiated a fee and scope of services for the [Phase 300/350] detailed final design and bidding of the Wakarusa WWTP, Pump Station No. 10, and Kansas River WWTP Lab Improvements as well as [Phase 400/500] construction phase services for the force mains, roads adjacent to the Wakarusa WWTP, and Wakarusa WWTP site fill.
The fee of $4,697,254.00 for Supplement Agreement No. 4 includes basic architectural/engineering (A/E) design services as well as the following non-basic A/E services:
· Geotechnical sub-consultant coordination
· Extensive permitting
· Bid phase services in Phase 350
· Construction phase contract administration in Phase 400
· Resident Engineer Services with full-time inspection during construction in Phase 500
Below is a breakdown of the proposed engineering services fee for the project in relation to preliminary construction cost estimates.
Estimated Construction Cost: |
$62,778,000 |
Basic A/E Design Services: |
$ 4,935,452 (7.86%) |
Non-Basic A/E Services: |
$ 1,714,330 (2.73%) |
Total A/E Services included in Original ESA & Supplements 1-4: |
$ 6,649,782 (10.59%) |
Total A/E Services estimated through project completion: |
$12,000,000 (19.0%) |
Adopted Basic A/E Fee Curve % of Estimated Construction: |
6.99% |
Design fee guidelines were adopted by the City of Lawrence on January 11, 2011 and included in the Citys Purchasing Procedures. The basic A/E design fee amount as a percentage of estimated construction cost as listed above at 7.86% is slightly higher than the design fee guideline percentage of 6.99% for projects of this size. However, a majority of the special circumstances listed in the design fee guidelines apply to this project, including the following:
In addition, the UT1304 Wakarusa WWTP and Conveyance Corridor project will consist of at least 8 different construction contracts. Below is a list of the preliminary construction cost estimates for each of those smaller projects and the corresponding basic A/E fee recommended by the design fee guidelines.
UT1304 Contract 1: Haskell Casing Pipe Installation |
|
Estimated Construction Cost: |
$88,600 |
Adopted Fee Curve % of Estimated Construction: |
11.5% |
UT1304 Contracts 2A: Force Mains, Fiber Optic, and Baker Wetlands Improvements |
|
Estimated Construction Cost: |
$8,600,000 |
Adopted Fee Curve % of Estimated Construction: |
6.99% |
UT1304 Contracts 2B-2C: Baker Wetlands Improvements |
|
Estimated Construction Cost: |
$300,000 |
Adopted Fee Curve % of Estimated Construction: |
9.75% |
PW1405 WWTP Access Roads (N1175 and E1600) |
|
Estimated Construction Cost: |
$2,800,000 |
Adopted Fee Curve % of Estimated Construction: |
7.4% |
UT1304 Contract 3 WWTP Site Fill |
|
Estimated Construction Cost: |
$4,200,000 |
Adopted Fee Curve % of Estimated Construction: |
7.2% |
UT1304 Contract 4 Kansas River WWTP Lab Improvements |
|
Estimated Construction Cost: |
$2,000,000 |
Adopted Fee Curve % of Estimated Construction: |
7.7% |
UT1304 Contract 5 Pump Station No. 10 |
|
Estimated Construction Cost: |
$6,400,000 |
Adopted Fee Curve % of Estimated Construction: |
6.99% |
UT1304 Contract 6 Wakarusa WWTP |
|
Estimated Construction Cost: |
$38,300,000 |
Adopted Fee Curve % of Estimated Construction: |
6.99% |
As illustrated above, a variance from the guidelines is reasonable based on the list of special circumstances and the various sizes of construction contracts within this larger project.
Also, the proposed scope and fee for design and construction phase engineering services for the project are commensurate and appropriate based on comparisons to similar-sized WWTP projects in other communities and the complexity of our project related to coordination with the SLT construction, enhancements within Baker Wetlands, extensive permitting requirements, and multiple project sites and construction phases.
Total engineering fees for similar-sized WWTP projects are summarized below.
Cedar Creek WWTP (Olathe, KS) |
|
Final Construction Cost: |
$ 35,118,502 |
Total ESA: |
$ 6,147,734 (17.5%) |
Columbia, MO WWTP |
|
Final Construction Cost: |
$ 55,220,000 |
Total ESA: |
$ 9,354,000 (16.9%) |
Grand Island, NE WWTP |
|
Final Construction Cost: |
$ 16,678,000 |
Total ESA: |
$ 3,397,255 (20.4%) |
Johnson Countys Douglas L. Smith Middle Basin (DLSMB) Treatment Plant |
||
Final Construction Cost: |
$ 30,800,000 |
|
Total ESA: |
$ 5,574,000 (18.1%) |
|
It is essential that the proposed facilities run efficiently for decades and a high quality design will help the City to save on operation and maintenance costs and reduce the potential for change orders during construction. Utilities Department Staff recommends this proposed scope of services that provides value with appropriate design considerations to improve operational capabilities, minimize energy use, and allow flexibility to grow the system as needed in the future.
Project Schedule
Detailed design of the Wakarusa WWTP and Pump Station No. 10 will be completed by early 2015 for construction on these facilities to begin in April 2015. Construction on PS No. 10 is expected to be complete by the end of 2016, and the Wakarusa WWTP construction is scheduled to be complete by the end of 2017.
As shown on the updated project workflow diagram, future amendments to the engineering services agreement will be presented for Commission approval for the following phases:
Phases 400/500 |
Construction and Resident Services |
Phases 600/700 |
Operations and Warranty Services |
Attached is a list of anticipated milestones for the UT1304 project. Tentative dates for City Commission agenda items are shown for the numerous design and construction contracts associated with this project.
Project Funding
The project is included in the Department of Utilities Rate Plan and Capital Improvement Program. An essential next step for this project will be approval of the necessary rate increases that follow the rate plan adopted last year. The rate increase proposals will be part of the upcoming budget season.
Action
Authorize the City Manager to Execute Supplemental Agreement No. 4, in the amount of $4,697,254.00, to the Existing Engineering Services Agreement with Black & Veatch Corporation for Project UT1304 Wakarusa Wastewater Treatment Plant and Conveyance Corridor Facilities.
Thank you for your assistance. Please advise if you have any questions.