Update on Phase 1 sidewalk inventory project.

 

Please include the following item on the City Commission City Manager’s Report for the April 22, 2014 meeting.

 

Status Update

The Public Works Department has completed the data collection portion of the phase 1 sidewalk inventory project. Over the next week Public Work’s staff will review and edit the data. Upon completion we will have estimates showing cost along with types of defects identified.

 

The attached map shows progress by locations of the inventory.