Memorandum
City of Lawrence
Public Works
TO: |
David Cronin, P.E., City Engineer |
FROM: |
Nicholas Voss, E.I.T., Project Engineer |
CC: |
Mark Thiel, Assistant Director of Public Works Charles F. Soules, P.E., Director of Public Works
|
Date: |
April 1, 2014 |
RE: |
Project No. PW1314 – Vermont Street, 21st to 22nd Street Brick Street Reconstruction – City Bid No. B1427 |
Please include the following item on the City Commission consent agenda for consideration at the April 15, 2014 meeting:
Project Description
Vermont Street from 21st Street to 22nd Street is currently a brick street in poor condition with a PCI rating of 13 (out of 100). This project proposes a complete reconstruction of this brick street. The project includes the removal of the existing brick pavement surface, a flyash treated subgrade, seven inches of asphalt, one inch of sand, and new brick pavers designed to match existing brick pavers used on City of Lawrence streets. The existing brick pavers have deteriorated past the condition where they would be able to be reused. The project is located outside of the city's historical environs. The project includes a traffic calming semi-diverter on the north end of the intersection of 23rd and Vermont Street that was recommended for approval by the Traffic Safety Commission on November 4th, 2013. The semi-diverter would restrict vehicles traveling on 23rd street from traveling onto Vermont Street and would resemble the semi diverters located at 6th & Schwarz Road and 7th & Rhode Island.
Project Funding
The project is in the 2014 budget, and is being funded with street maintenance funds and motor fuel sales tax.
Project Schedule
Advertise: April 16, 2014
Bid date: April 29, 2014
Award Contract: May 6, 2014
Anticipated Start Date: May 26, 2014
Project Completion Date: August 8, 2014
Action Request
Set bid date of April 29, 2014 for PW 1314, Vermont Street, 21st to 22nd Street Brick Street Reconstruction.