Located at the southeast corner of 11th Street and Rhode Island Street, the 1106 Rhode Island Street property is 0.268 acres in size with three structures identified as contributing to the North Rhode Island Street Historic Residential District, National Register of Historic Places: the house, garage, and large barn. The City recently acquired the property (purchase price of $114,500) at 1106 Rhode Island Street, which had been subject to long-standing code violations leading to condemnation.
The City has a desire to see the historic property rehabilitated to productive use. After the City’s ownership of the property was finalized, the City distributed an RFP on March 28, 2014 seeking proposals from firms and individuals interested in purchasing the property and rehabilitating the existing house, large barn and garage located on the property. In response to that RFP, the City received one proposal, submitted by Hernly Associates, Inc.
Proposal Overview:
The Hernly Associates submission proposes retaining the buildings on site that are considered “Contributing” to the North Rhode Island Street Historic Residential District and adding new space that enhances the usefulness of the property. The redevelopment plan includes the following:
Proposed Uses |
||
House |
S.F. |
|
Finished Area: |
1,547 (1,162 rehab + 385 new) |
|
Basement (existing unfinished): |
315 |
|
Garage: |
228 |
|
Apartment |
S.F. |
|
New Finished Area: (1 bedroom, 1 bath) |
718 |
|
Garage: |
228 |
|
Professional Office in Warehouse/Garage |
S.F. |
|
Rehab Areas: |
2,170 |
|
Existing Open Space |
S.F. |
|
Existing open area of NWC of lot |
To remain open space |
|
Preliminary site plan and concept drawings were provided by the developer and are included within the proposal.
Project Costs:
Total project costs are estimated at $896,600 and include:
Proposed Purchase Price:
As per the developer, the property would be worth more if the building were demolished and removed rather than left in place. “The ‘improvements’ (i.e. the buildings) on the property have been allowed to languish for so long, they actual subtract from the value of the property rather than add to the property.” Based on the property as-is, the developer is proposing a purchase price of $90,000.
Value of 1106 Rhode Island as vacant land (Keller appraisal) |
$105,000 |
Cost to demolish all structures (bid from subcontractor) |
$9,500 |
Cost to disconnect all utilities (estimate) |
$500 |
Cost to obtain demolition approval through City processes (estimate) |
$5,000 |
Value of 1106 RI with buildings in place as-is |
$90,000 |
Proposed Assistance:
According to the developer, residential and office market rental rates alone will not support the cost of redevelopment. For the redeveloped property to maintain a positive cash flow, additional financial support is required, including State and Federal Preservation Tax Credits, State and Local Preservation Grants, a City Development Grant (rebating fees and permit costs), and the establishment of a Neighborhood Redevelopment Area (NRA).
Development Grant: Proposed Rebate of Project Fees |
|
Replat submittal/review fee rebate |
$200 |
Rezoning submittal/review fee rebate |
$200 |
Site Plan submittal/review fee rebate |
$200 |
BZA submittal/review fee rebate |
$200 |
Demolition Permit for out buildings and rear porch on house rebate |
$50 |
Building Permit fee rebate |
$3,950 |
Dumpster during construction rebate |
$3,450 |
Water service connections house/apartment and office--rebate from utility funds for installation of new water service lines |
$7,350 |
Sanitary sewer service connections house/apartment and office--rebate from East Lawrence sanitary sewer system upgrade program |
$10,500 |
Total Estimated Financial Assistance from City |
$26,100 |
Timeline:
The developer anticipates a 15-18 month timeframe to accommodate property purchase, rezoning, demolition, approvals and construction. Future action items specified within the proposal include:
Action Items |
Execute purchase agreement |
Submit rezoning application |
Submit concept plans for preliminary review to Kansas Historical Society (KSHS) & National Park Service (NPS) |
Organize development group as LLC |
Final approval of rezoning |
Preliminary approval of design concept by KSHS and NPS |
Purchase the property |
Submit site plan for review & approvals |
Submit design plans for HRC review |
Submit BZA application for setback variances |
Submit demolition application |
Prepare construction drawings |
Obtain contractor bids |
Submit application for Historic Preservation Tax Credits |
Submit application for preservation grant |
Negotiate NRA tax rebate agreement |
Negotiate City development grant |
Rehabilitate existing building, construct new additions, and complete site improvements |
Staff Recommendation:
A selection committee of City staff and Historic Resources Commission (HRC) representatives reviewed the proposal on April 4, 2014. The committee recommends analysis of economic development support requested and review and recommendation by the Public Incentives Review Committee (PIRC).
Requested Actions:
Receive proposal for purchase and rehabilitation of 1106 Rhode Island Street property. Refer to staff for analysis of requested economic development support and PIRC for review and recommendation.