Memorandum
City
of Lawrence
Public
Works / Utilities Department
TO: |
David L. Corliss City
Manager Cynthia Wagner Assistant
City Manager Diane Stoddard Assistant
City Manager Casey Toomay Budget
Manager |
FROM: |
Leah Morris Project Engineer Charles F. Soules
Director of Public Works |
CC: |
Dave Wagner Director of
Utilities Mike Lawless Deputy
Director of Utilities Philip Ciesielski
Assistant Director of Utilities David Cronin City
Engineer Beth Krishtalka Assistant to Director Bob Brower Utilities Field Superintendent Mark Hegeman Utilities Operations Superintendent Dave King Utilities Maintenance Superintendent |
Date: |
March 17, 2014 |
RE: |
Agenda
Item Authorize the
Mayor to Execute Supplemental No. 1 to the City State Agreement No. 12-12
with Kansas Department of Transportation Addressing Utilities and Public
Works items related to the Construction of the South Lawrence Trafficway. |
Please include the following item on the
City Commission Agenda for consideration at its March 25, 2014 meeting:
Authorize
the Mayor to Execute Supplemental No. 1 to the City State Agreement No. 12-12
with Kansas Department of Transportation addressing Utilities and Public Works
items related to the construction of the South Lawrence Trafficway and 31st
Street.
Project
Background - Utilities
The South Lawrence Trafficway (SLT) is
currently under construction by Emery Sapp & Sons, the general contractor
for the Kansas Department of Transportation (KDOT). Required watermain and
sanitary sewer relocations in the area of 31st and Haskell were
designed and bid as part of the KDOT SLT project due to the required
construction sequencing in this area. The construction of these relocations
will be paid for by the Department of Utilities.
Per KDOTs direction, the design and
proposed construction of additional sanitary sewer relocations and the
extension of a watermain in the area of 31st and Louisiana were put
forth as projects to be bid and constructed by the City of Lawrence separately
from the SLT project. Approximately 4,000 linear feet of 12 diameter watermain,
and 5,100 linear feet of sanitary sewer will be constructed in this area (see attached map).
The Department of Utilities contracted with
HNTB, the design firm for the SLT project, for design of the required sanitary
sewer and watermain relocations in this area. HNTB have completed the plans and
specifications, and City staff has acquired the necessary easements.
Project
Status - Utilities
Construction in the area of 31st
and Louisiana has become a complicated scheduling and construction sequencing
issue due to the ongoing relocation of Southern Star Petroleums 16 diameter
pipeline and a Black Hills Energy natural gas main. These pipelines conflict
with both the SLT project and the new location of the City of Lawrence sanitary
sewers and watermain. At this time, neither utility has a firm timeline for the
relocation of their existing pipelines. As a result, the City cannot include
construction schedule information within its project bid documents to meet the
mandated KDOT relocation dates and avoid delays to the SLT project. Delays in
the relocation of utilities in conflict with the SLT construction which
ultimately delay Emery Sapp & Sons work on the SLT will result in
significant penalties assessed by KDOT.
The City Commission approved the negotiation of a City State
Agreement with KDOT on January 7, 2014.
Staff negotiated a Supplement to the current City State Agreement with
KDOT, including payment to KDOT for the construction of the required sanitary
sewer and watermain relocations in the area of 31st and Louisiana in
the negotiated amount of $2,001,542. The improvements will be constructed by
KDOTs SLT contractor Emery Sapp and Sons under a change order to their SLT
contract with KDOT. All costs associated with these relocations are being paid
by the Department of Utilities.
Project Status Public
Works
In May 2012, the City entered into an agreement with the Secretary of
Transportation to include the construction of 31st Street with the
South Lawrence Trafficway Project.
Within that agreement KDOT also acquired the right-of-way needed for 31st
Street to be reimbursed by the City.
In review of the 31st Street project, the Corps identified
approximately 11 acres of wetlands that the City needed to mitigate. KDOT verbally agreed to allow the City to use
excess property that they acquired for the SLT mitigation plan that would
enhance the Baker Wetland Project. The
approximate cost was $6,500/acre. The
City has also entered into an agreement with Baker University to accept this
property and construct, manage and maintain the wetland for the City of
Lawrence.
The Supplemental Agreement reiterates the agreement for property
acquisition for the construction of 31st Street and also formally
consummates the agreement for the wetland mitigation property between the City
and KDOT.
Action Request
Authorize
the Mayor to Execute Supplemental No. 1 to the City State Agreement No. 12-12
with Kansas Department of Transportation addressing Utilities and Public Works
items related to the construction of the South Lawrence Trafficway and 31st
Street.