Memorandum

City of Lawrence

Public Works

 

TO:

David P. Cronin, P.E., City Engineer

 

FROM:

Zachary D. Baker, E.I.T., Project Engineer

 

CC:

Charles F. Soules, P.E., Director of Public Works

Mark Thiel, Assistant Director of Public Works

 

Date:

March 25, 2014

 

RE:

Project PW1302 – 9th Street – Avalon Road to Arkansas Street

City/State Agreement; KDOT Project U-0161-01

 

Project Description

The 9th Street and Emery Road project includes the installation of new traffic signals at 9th Street and Emery Road, new sidewalks and ramps, a mill and overlay of 9th Street, and new pavement markings.  The lane configuration of 9th Street is currently two eastbound and two westbound lanes.  A proposed new 3-lane configuration will be restriped to allow for one through lane in each direction for east and westbound traffic on 9th Street, a center left turn lane between Emery and Michigan, and two new bike lanes beginning just west of Michigan Street and continuing west near Avalon Road. The turn lane addition is intended to help alleviate traffic accidents that have been prominent at both Emery and Michigan Street intersections due to left turn movements off of 9th Street. A traffic analysis has been done modeling the new 3-Lane configuration and levels of service (LOS) will not be negatively affected as the 9th Street and Emery Road intersection LOS will continue to have an AM peak hour “A” rating and a PM peak hour “B” rating.

 

Project Funding

The project is being funded with Federal-aid funds that cover ninety percent (90%) of the participating construction and construction engineering costs (inspection) with a project cap of $325,000. The remaining ten percent (10%) and all other costs associated with the project are funded by the city from general obligation bonds approved in Resolution No. 7053 in the amount of $50,000. The project cost does not include the cost of engineering design or construction engineering services.  Public Works staff is designing the project in-house and will be providing construction inspection.

 

Project Schedule

Final Plans: April 16, 2014

Advertise and Bidding: May 2014

Anticipated Start Date: June 30, 2014

Project Completion: August 31, 2014

 

Action Request

If appropriate authorize the Mayor to execute an Agreement with the Kansas Department of Transportation for the 9th Street, Avalon Road to Arkansas Street, improvements, Project No. PW1302.