Memorandum
City
of Lawrence
Utilities
Department
TO: |
David L. Corliss – City Manager Cynthia Wagner - Assistant
City Manager |
FROM: |
|
CC: |
Dave Wagner – Director of Utilities Mike Lawless – Deputy Director of Utilities Beth Frailey Krishtalka – Assistant to Director Mark Hegeman – Utilities
Operations Superintendent Dave King – Utilities Maintenance Superintendent |
Date: |
February 19, 2014 |
RE: |
Authorize the Purchase of a Motor and Variable Frequency Drive for
Clinton Raw Water Pump 4, and set a bid date of March 25, 2014 for Bid Number
B1413, Project UT1407 - Installation
of a Motor and Variable Frequency Drive for Clinton Raw Water Pump 4 |
Please include the following item on the
City Commission Agenda for consideration at the February 25, 2014 meeting:
Authorize the execution of a purchase
agreement with Logic Inc. in the amount of $93,807.19 plus actual shipping
costs for the purchase of an ABB Variable Frequency Drive (VFD) and Baldor Motor with a 5 year warranty per Quote 206308 for Clinton Raw Water Pump 4.
Set a Bid Date of March 25, 2014 for
Bid B1413 Project UT1407 for the installation of a motor and VFD for Clinton
Raw Water Pump 4.
Project
Description:
The Clinton Water Treatment Plant receives
raw water from the Clinton Reservoir via pumping at the Raw Water Pump Station
located adjacent to the dam outlet structure (see the attached map). The pump
station has 4 raw water pumping units; 2 each rated at 5 million gallons per
day (MGD) and 2 each rated at 10 MGD.
Pump 4 is a 300hp, 10 MGD pump equipped with a VFD for variable speed control installed as part of the 2001 Clinton WTP Expansion. This pump, motor and VFD combination has had issues with motor damage occurring when run at full speed. Over the last several years the pump has been run at a reduced speed, and flow, to overcome these issues. As water demand has increased, the Department needs to be able to run the unit at full speed, and flow, to reliably meet peak demands.
In an attempt to correct the ongoing issues and keep the unit in service on a limited basis, over the last year the Department expended $14,560 on repairs to the existing VFD and $25,123 on the motor. These repairs currently have the pump serviceable, but only at reduced speeds and flows.
Project Status:
Staff investigated the performance issues and determined the replacement of the motor and VFD is required to bring the pump back to full service. In an effort to eliminate the question of responsibility for the performance of the system, staff recommends the new motor and VFD be provided by a single supplier. Staff negotiated the referenced quote for both the motor and VFD, startup services, and a 5 year warranty with Logic Inc.. Logic Inc. is the local supplier for the department’s specified standard ABB VFDs. Logic Inc. will be providing and warranting a Baldor motor as part of the package.
Staff recommends executing a separate
purchase agreement for the equipment and bid for the installation to compress
the overall project schedule and have the new equipment installed and ready for
service ahead of mid-summer peak summer demands. The delivery for the motor and
VFD is 10 weeks after order approval. It is anticipated removal of the existing
equipment, and installation and startup of the new motor and VFD will take two
weeks.
Project Funding:
The project is funded from the 2014 Operations and Maintenance budget.
Action
Request:
Authorize the execution of a purchase
agreement with Logic Inc. in the amount of $93,807.19 plus actual shipping
costs for the purchase of an ABB Variable Frequency Drive (VFD) and Baldor Motor with a 5 year warranty per Quote 206308 for Clinton Raw Water Pump 4.
Set a Bid Date of March 25, 2014 for
Bid B1413 Project UT1407 for the installation of a motor and VFD for Clinton
Raw Water Pump 4.
Thank you for your
assistance. Please advise if you have any questions.