Memorandum

City of Lawrence

Public Transit Office

 

DATE:

12/11/13

TO:

David L. Corliss, City Manager

FROM:

Robert A. Nugent, Transit Administrator

CC:

Diane Stoddard, Assistant City Manager

Cynthia Wagner, Assistant City Manager

RE:

RFP R1316 - Contracted Public Transportation Services for the City of Lawrence and University of Kansas

 

Please place the following item on the City Commission agenda for consideration at their December 17, 2013 meeting:

 

Authorize City Manager to enter into a contract with MV Transportation, Inc. for public transportation services beginning January 1, 2014. 

 

Background

The current contract with MV Transportation, Inc. to provide public transportation services expires December 31, 2013. In August of 2013, the City and the University of Kansas issued a joint Request for Proposals for public transportation services from January 1, 2014 through December 31, 2018.  The City received bids from First Transit, Inc. and MV Transportation, Inc.  After reviewing the proposals, interviewing the candidates, and receiving several rounds of follow up questions, the Purchase Negotiating Committee (PNC) comprised of both City and University staff recommended selecting MV as the contract provider.  The City Commission accepted that recommendation and authorized staff to enter into negotiations with MV on
October 8, 2013. Although the RFP was jointly issued, each entity is negotiating a separate contract. 

 

Contract Summary

The contract was drafted using the existing contract as a starting point.  It incorporates by reference the RFP, MV’s Proposal, and addendum. The Scope of Work is contained in Part II of the RFP, as revised by addendum and shall constitute all of work to be provided. The highlights, as well as any changes are summarized below.

 

 

 

 

 

 

·         Vehicles - The City will provide all revenue hour vehicles for this contract. This includes both fixed route and paratransit vehicles.

 

 

 

 

 

 

Contract Period

Rate / Revenue Hour

(Variable)

Rate / Service Month

(Fixed)

Cost of MV  Contract

1/1/14  to 12/31/14

36.32

65,203

$3,576,161

1/1/2015 to 12/31/2015

35.16

65,192

$3,486,808

1/1/2016 to 12/31/2016

35.46

67,273

$3,534,960

1/1/2017 to 12/31/2017

35.71

69,043

$3,575,466

1/1/2018 to 12/31/2018

36.32

71,150

$3,647,987

 

For comparison purposes the rates under the existing contract are as follows:

 

Contract Period

Rate / Revenue Hour

(Variable)

Rate / Service Month

(Fixed)

1/1/09 to 12/31/09

30.77

72,291

1/1/10 to 12/31/10

31.93

75,307

1/1/11 to 12/31/11

32.54

65,515

1/1/12 to 12/31/12

33.90

68,075

1/1/13 to 12/31/13

35.41

70,593

 

The new contract also notes that the rates are subject to change pending cost allocation review between the City and University.  Pricing in MV’s response to the RFP assumed that the City would pay 56% of the total costs while the University would pay 44% based on the percentage of total service hours to be provided

 

 

 

 

 

The Contractor has also been developing a smart phone “app” that will also be made available to the general public. Although not finished the Contractor commits to provide the City and the University versions of the new “app” in the immediate future. The Contractor is also committed to having the “app” ready to be provided to the general public on January 20, 2014.

 

 

Contract Funding

The table below compares the annual total operating cost to the projected revenue generated by FTA annual formula grant funds, Kansas CTP grant, the 0.2% sales tax, and farebox proceeds.

 

2014

2015

2016

2017

2018

Carry Forward

5,820

86,205

393,247

696,379

Estimated Revenues:

FTA Section 5307 Grant

2,220,420

220,420

2,220,420

2,220,420

2,220,420

Assumes 0% annual

Kansas CTP Grant

529,148

529,148

529,148

529,148

529,148

Assumes 0% annual

Local .20% Sales Tax

2,955,738

2,985,295

3,015,148

3,045,299

3,075,752

Assumes 1% annual

Fare Revenue

317,498

320,672

323,879

327,118

330,389

Assumes 1% annual

TOTAL REVENUES

6,022,804

6,161,355

6,374,800

6,815,232

7,252,088

Estimated Expenditures:

Personnel

$                      278,415

283,983

289,663

295,456

301,365

Assumes 2% annual

Operating Contract

3,576,161

3,486,808

3,534,960

3,575,466

3,647,987

At no additional service

Route Enhancements

715,232

697,362

706,992

715,093

729,597

Assumes 20%

Other Contractual

100,000

102,000

104,040

106,121

108,243

Assumes 2% annual

Commodities

731,426

767,997

806,397

846,717

889,053

Assumes 5% annual

Capital Outlay

615,750

637,000

339,500

280,000

280,000

TOTAL EXPENDITURES

6,016,984

5,975,150

5,781,552

5,818,853

5,9856,246

Balance:

5,820

86,205

393,247

 696,379

895,842

 

Recommendation

Staff recommends the City Commission authorize the City Manager to enter into a contract with MV Transportation for public transportation services from January 1, 2014 to December 31, 2018. 

 

Requested Action

Staff seeks City Commission authorization to enter into a contract with MV Transportation for public transportation services.