Memorandum

City of Lawrence

Utilities Department

 

TO:

David L. Corliss – City Manager

Cynthia Wagner - Assistant City Manager

Diane Stoddard - Assistant City Manager

FROM:

Philip Ciesielski – Assistant Utilities Director

CC:

Dave Wagner – Director of Utilities

Mike Lawless –Utilities Deputy Director

Beth Krishtalka – Assistant to Director

Mark Hegeman – Utilities Operations Superintendent

Dave King – Utilities Maintenance Superintendent

Date:

October 16, 2013

RE:

Agenda Item – Set a Bid Date for Bid Number B1359, Project UT1102KA Kaw WTP Raw Water Intake Replacement

 

Please include the following item on the City Commission Agenda for consideration at the October 22, 2013 meeting:

 

Set a Bid Date of November 19, 2013 for Bid Number B1359, Project UT1102KA Kaw WTP Raw Water Intake Replacement

 

Project Description

The project provides for the construction of a redundant surface water intake and raw water pipeline to the Kaw Water Treatment Plant (WTP), and modifications to and dredging in the area of the active intake as recommended in the November 2012 Kaw Water Treatment Plant Raw Water Intake Evaluation by Black & Veatch. The construction of the new intake and raw water pipeline will provide a redundant point of raw water diversion from the Kansas River for the Kaw WTP. These facilities will also serve as the first phase of Kansas River raw water supply required for the potential expansion of the Kaw WTP to a treatment capacity of 25 MGD. The modifications to the existing intake involve raising the top to above the new water surface as impounded by Bowersock Dam, installing a sediment shield on the intake pipe to reduce the intake of sand into the pipe and Low Service Pump Station No.2, and dredging in the immediate area of the intake. Additionally the two (2) abandoned intakes and piping will be removed. See the attached map indicating the location of the work.

 

Project History

January 24, 2012 - City Commission authorized execution of the Engineering Services Agreement for the work.

 

September 5, 2012 - Received draft report.

 

September 20, 2012 - Provided Staff review comments to Black & Veatch.

 

November 20, 2012 - Received updated report.

 

December 18, 2012 – City Commission authorized execution of Supplemental Agreement for the design of immediate modifications to the existing intake structure and dredging of accumulated river bed material in the vicinity of the intake. These improvements are currently being designed and permitted with dredging expected to take place this summer and construction of the modifications during fall and winter.

 

March 12, 2013 – City Commission authorized Staff to negotiate a Supplemental Agreement with Black & Veatch for engineering services related to the construction of a new intake and raw water piping.

 

May 7, 2013 – City Commission authorized the execution of a Supplemental Agreement with Black & Veatch for engineering and construction phase services for the project.

 

October 1, 2013 – Staff provided an update on the status of the project on the City Manager’s Report.

 

Project Status

Black & Veatch have completed the construction documents and the project is ready to advertise for bidding. The project has been approved and permitted by the US Corps of Engineers. The project documents have been submitted to KDHE and the Kansas Division of Water Resources for review and permitting. Award of the contract will be pending receipt of these permit approvals.

 

Project Schedule                Days From Notice to Proceed

City Commission Set a Bid Date      October 22, 2013

Prebid Meeting                            November 5, 2013

Bid Opening                                November 19, 2013

Milestone 1 New Intake Complete   May 15, 2014

Substantial Completion                  June 15, 2014

Final Completion                          July 1, 2014

 

Project Funding

The project is included in the Department of Utilities 2013 Capital Improvements and Rate Plan and is identified in the proposed Bond Funds per Resolution 7019.

 

Action Request: Set a Bid Date of November 19, 2013 for Bid Number B1359, Project UT1102KA Kaw WTP Raw Water Intake Replacement

 

Thank you for your assistance. Please advise if you have any questions.