Memorandum

City of Lawrence

Parks & Recreation Department

 

DATE:

October 9, 2013

 

 

TO:

Dave Corliss, City Manager,

 

Cynthia Wagner, Assistant City Manager

 

Diane Stoddard, Assistant City Manager

 

Ernie Shaw, Interim Director Parks & Recreation

 

 

FROM:

Mark Hecker, Assistant Director, Parks and Recreation

 

 

RE:

Bid recommendation – 2013 Master Street Tree Project

 

On October 8, 2013, Parks and Recreation Department opened bids for the 2013 Master Street Tree Program. This project bid the purchase and installation of 184 street trees.

 

Rosehill Gardens was the only vendor that bid the project at a cost of $225.00 per tree for the 2” tree, and $350 for the 3” trees, for a total cost of $42,150 for the 184 trees. The work would start immediately upon getting the trees dug this fall.

 

Funding for this project comes from the fees collected during the building permit process.

 

Recommendation Action:

Award the purchase and installation of 184 street trees to Rosehill Gardens at a total price of $42,150.