Project PW1127: 23rd and O'Connell Road - Street and Storm Sewer Reconstruction
|
Please include the following item on the City Commission Consent Agenda for consideration at the December 11, 2012 meeting.
Project PW 1127 - City Bid No. B1266, 23rd and O'Connell Road
VENDOR |
TOTAL |
Engineer's Estimate |
$663,166.50 |
King's Construction Co., Inc. |
$571,459.05 |
R. D. Johnson Excavating Company, Inc. |
$591,851.25 |
Amino Brothers Co., Inc. |
$665,460.56 |
Freeman Concrete Construction, LLC |
$699,816.40 |
Project Description
The 23rd & O'Connell project includes geometric improvements at the intersection of 23rd Street & O'Connell Road, signalization of the 23rd Street & O'Connell Road intersection, concrete pavement, concrete curb and gutter, 2" mill and overlay, and storm sewer work. Major items of the proposed geometric improvements include:
1. An eastbound left turn lane at 23rd Street & O'Connell Road
2. Concrete medians on 23rd Street
3. Then construction of a new approach for O'Connell Road north of the intersection of 23rd Street & O'Connell Road.
Traffic will be maintained with two lanes eastbound and westbound throughout the project, and access will be maintained to all adjacent properties. Because of the lead time to order traffic poles, construction of the traffic signal will be completed by May, 2013. All other construction is anticipated to be completed by March 30th, 2013.
Project Cost / Funding
The project will be funded with General Obligation Bonds from Resolution No. 6940.
Bid Evaluation / Recommendation
Staff has evaluated all bid proposals to check for accuracy, completeness and other applicable criteria. As shown in the Summary Table, the bid proposal from King's Construction Co., Inc. offers the lowest and best total bid price for this project. Staff recommends “Award of City Bid No. B1266” to King's Construction Co., Inc.
Action Request
Award City Bid No. B1266: 23rd and O'Connell Road to King's Construction Co., Inc. in the amount of $571,459.05 provided the contractor can meet the terms established in the contract documents.