Fire Apparatus Inspection and Delivery Schedule |
The following schedule outlines the estimated Inspection and Delivery dates of the three new pieces of fire apparatus. They include two 75’ Quints and one Technical Rescue Vehicle.
Quints
Cost - $831,826.00 ea
Inspection Trip – Week of March 23, 2009
Delivery to Lawrence – Week of March 30, 2009
In-service Date – Week of June 1, 2009
Once the vehicles are delivered the following inspections and training is conducted:
· Central Vehicle Maintenance performs delivery inspections;
· Manufacture training is performed;
· Installation of equipment;
· Department driver/operator training.
Technical Rescue
Cost - $621,521
Inspection Trip – Week of May 3, 2009
Delivery to Lawrence – Week of May 11, 2009
In-service Date – Week of July 20, 2009
Once the vehicles are delivered the following inspections and training is conducted:
· Central Vehicle Maintenance performs delivery inspections;
· Manufacture training is performed;
· Installation of equipment;
· Department driver/operator training.
As you recall the City authorized the sole source purchase of these three vehicles off the HGAC contract. This contract purchase saved an estimated $180,000 to $230,000 in administrative time and actual vehicle costs.