[E-updates] CITY INFRASTRUCTURE IMPROVEMENT PROJECTS for weeks of Nov. 20 and Nov. 27

Lisa Patterson lpatterson at ci.lawrence.ks.us
Fri Nov 17 08:59:47 CST 2006


NEWS RELEASE
 
City of Lawrence, Kansas
FOR IMMEDIATE RELEASE
 
Friday, Nov. 17, 2006
 
CONTACT: Lisa Patterson, communications manager, (785) 832-3406
 
CITY INFRASTRUCTURE IMPROVEMENT PROJECTS
 

(LAWRENCE, Ks) - No new projects are scheduled to begin next week.
There are no changes in traffic impacts planned for next week.

 

The week of Nov. 27, crews will install a fire hydrant at the northwest
corner of 31st and Iowa Streets and will work in a portion of the
southbound right turn lane of Iowa Street.  Work will be ongoing for
approximately two days, weather permitting and right turns will be
permitted.

 

Work on the Riverfront Parking Garage will progress the week of Nov. 27
and the ramp between levels may be opened to through traffic, weather
permitting.  When the ramp opens, crews will close the New Hampshire
Street entrance for surface repairs.  Access to the upper and lower
levels of the garage will be via the Rhode Island Street entrance.  

 

On Dec. 2, a parade will begin at 11:00 at Seventh Street and
Massachusetts and travel south.  During the parade, the Lawrence Transit
System will move lay over points to the east and west of Ninth and
Massachusetts Streets.  Passengers using the bus in Downtown should move
to either Ninth Street and Vermont or Ninth Street and New Hampshire.

 

On going city infrastructure improvement projects for the weeks of Nov.
20 and Nov. 27 include:
 
Project: Kasold bridge over KTA
Traffic impact:
Kasold, north of Peterson Road, closed to through traffic
 
Project: Kasold Drive reconstruction
Traffic impact:
Kasold Drive, Bob Billings Parkway to W 22nd Street, one lane traffic
each direction
22nd Street east of Kasold Drive, right turns permitted, left turn
prohibited
Kasold Drive, intersections with all side streets, closed from Bob
Billings Parkway to W 22nd Terrace
 
City street crews

Bob Billings Parkway, Iowa Street to Kasold Avenue, reduced to one lane
in sections during the work day

 

Project: sanitary sewer pump stations in North Lawrence

Traffic impact:  as work progresses, these impacts may occur

North Street, residence and business access will be maintained

Grant Street, residence and business access will be maintained

Walnut Street, residence and business access will be maintained

 

Project: Waterline installation

Fair Lane, west of Maple Lane, completed

Wedgewood Drive, 15th Street to Random Road, completed

 

Riverfront parking garage at Sixth and New Hampshire

Ramp between upper and lower level closed

Week of Nov. 27, possible opening of the ramp and closing of New
Hampshire Street entrance

 

Week of Nov. 27 - fire hydrant installation

31st and Iowa Streets, northwest corner, shortened length of the
southbound right turn lane of Iowa Street while crews work

 

-END-

 

 

_____________________________

 

Lisa K. Patterson |Communications Manager

City of Lawrence

PO Box 708 | Lawrence, KS 66044

(785) 832-3406

fax (785) 832-3405

lpatterson at ci.lawrence.ks.us

www.lawrenceks.org

 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://web.ci.lawrence.ks.us/pipermail/e-updates/attachments/20061117/9c396d06/attachment.html


More information about the E-updates mailing list