City infrastructure improvement projects 

(LAWRENCE, KS) - No new projects are scheduled to begin the week of Nov. 22.

Working days assessed for on going city infrastructure projects are as of
Nov. 13.  On going city infrastructure improvement projects include:

Project:  13th and Oregon Storm water project
210 working days on the contract, project began March 9, 123 working days
assessed and 87 working days remaining
Original estimated completion date:  Feb. 2005, weather permitting
Current traffic impacts:
Pennsylvania, closed 13th Street to 14th Street

13th Street, closed at Oregon

Project: O'Connell Road street improvements, project complete
O'Connell Road, opened to through traffic on Nov. 18

Project: Trail Road sanitary sewer line
40 working days on the contract, work began Nov. 3, 8 working days assessed
and 32 working days remaining
Estimated completion date: Jan. 21
Traffic impact:
Trail Road, Jane Court to Roundabout Circle, occasional lane closures 

Folks Road, north of Trail Road closed during working day to through traffic

=========================
Lawrence Transit System does not have any reroutes scheduled during the week
of Nov. 22.

-END-

_____________________________
Lisa K. Patterson
Communications Coordinator
City of Lawrence
PO Box 708
Lawrence, KS 66044
(785) 832-3406
fax (785) 832-3405
lpatterson at ci.lawrence.ks.us
http://www.lawrenceks.org




More information about the E-updates mailing list