Images of Lawrence

City Commission Meeting Agenda

The 9-9-08 City Commission meeting is now online.

Construction

Current Construction

View Current Construction in the city.

Airport History

The formal opening of the Lawrence Airport, at its current location, was in 1929. The airport property was first owned by the university of Kansas, then deeded to the Kansas University Endowment Association and then sold to the City of Lawrence in 1977. Four runways were originally constructed on this site: a 2,600-foot northeast southwest runway, a 1,800-foot north/south runway, a 1,700-foot east/west runway, and a 1,250-foot northwest/southwest runway.

In 1936, the improvements included the surfacing of the four runways with three inches of cinders, boundary markers, a landing are markers circle; and concrete floors, aprons, and lighting were added to two hangers.

In 1941, the runways were extended to the following lengths:

Runway Length
Northeast/Southwest 3,200 feet
North/South 2,500 feet
East/West 2,460 feet
Northwest/Southeast Not Extended

In 1958, by Grant Agreement wit the Civil Aeronautics Administration, the predecessor to the Federal Aviation Administration, a new northeast/southwest, 3,000-foot runway (1-19) was constructed using a seven-inch soil cement bas and two inches of asphalt surfacing. Also constructed was a taxiway from the south end of the runway to the hangar area, a 150-foot by 340-foot apron, medium intensity runway lights, a lighted rotating beacon, and a natural gas line to the administration building. The administration building was enlarged to provide a waiting room, airport manager's offices, pilot's ready room, lounge, and restrooms.

During 1962 and 1963, additional clear zone aviation easements were obtained. In 1969, an 83-foot by 120-foot hangar was constructed to provide space for storage and complete repair service by the fixed base operator. A 30-foot by 150-foot T-hangar and a 30-foot by 170-foot tie-down slab were constructed to provide additional storage.

Following is a summary of airport improvement program projects completed at the airport since it was purchased by the City of Lawrence:

Date Grant No. Amount Items of Work Accomplished
1977 6-20-0047-01 $580,000 Acquire land and easement overlay, widen, extend, light (MIRL) and mark Runway 1-19; overlay, widen, mark and light connecting taxiway; construct segmented circle, lighted wind cone and road barriers; modify underground pipelines; install fencing; site preparation and drainage clearing, grubbing and obstruction removal.
1978 6-20-0047-02 $309,000 Acquire land; reimbursement for land; adjust pipeline.
1980 6-20-0047-03 $1,552,000 Acquire land; construct, mark and light (MIRL) Runway 14-32 (now 15-33); construct and mark connecting taxiway from Runway 32 (33) to Runway 1; construct and seal apron; grading, seeding and drainage.
1981 6-20-0047-04 $150,000 Grade apron; construct and mark access road to new terminal area; install lighted rotating beacon; drainage, seeding.
1982 3-20-0047-01 $939,000 Expand terminal apron including marking and tiedowns; construct and mark parallel taxiway; grading and seeding.
1983 3-20-0047-02 $155,000 Land reimbursement for airport development; light NW-SE parallel taxiway; apron lighting.
1990 3-20-0047-03 $22,500 Airport master plan update.
1990 3-20-0047-04 $969,021 Safety area grading and ILS.
1991 3-20-0047-05 $351,447 Approach lights and land acquisition.
1992 3-20-0047-06 $370,954 Pavement rehabilitation and marking.
1997 3-20-0047-07 $58,770 Apron rehabilitation.