CITY SHARE OF COUNTY-WIDE SALES TAX - DRAFT
2005– 2009 CAPITAL IMPROVEMENT BUDGET SUMMARY
Projects 2005 2006 2007 2008 2009
Misc. Maintenance Imp. (system wide) 75,000 75,000 100,000 100,000 100,000
Park Maintenance Facility Imp. 200,000 200,000 200,000 200,000 200,000
Park Land Acquisition 0 300,000 300,000 300,000 300,000
Bike Trail & Facility Development 0 50,000 150,000 150,000 150,000
Entryway Improvements 0 0 25,000 0 0
Peterson Park Improvements 0 0 0 250,000 150,000
Green Meadows Park 0 0 0 0 242,000
           
           
Sub-total 275,000 625,000 775,000 1,000,000 1,142,000
           
Debt:          
Aquatic Center (outdoor) 309,000 0 0 0 0
East Lawrence Center 247,000 251,000 0 0 0
Health Center/Indoor Aquatic Center 1,288,000 1,291,000 1,260,000 1,267,690 1,263,409
Adult Softball Complex 260,000 263,000 0 0 0
Sub-total 2,104,000 1,805,000 1,260,000 1,267,690 1,263,409
           
           
           
TOTAL 2,379,000 2,430,000 2,035,000 2,267,690 2,405,409
Note: this Plan does not purport to indicate that sufficient revenues will be available to complete all the listed projects.
Note: Given current sales tax trends, it is unlikely the sales tax (city share of county-wide sales tax) can support this debt and provide substantial operation, maintenance, and new project support.