WASTEWATER UTILITY - DRAFT
2005 – 2009 CAPITAL IMPROVEMENT BUDGET SUMMARY
Source: 2003 Wastewater System Master Plan
Projects 2005 2006 2007 2008 2009
Inflow/Infiltration Reduction Program $704,000 $732,000 $761,000 $791,000 $823,000
General Sanitary Sewer Improvements 649,000 675,000 702,000 730,000 $760,000
General Pump Station Improvements  217,000 225,000 234,000 244,000 254,000
General WWTP Improvements 217,000 225,000 234,000 244,000 254,000
KR-4-2 Pipe Project 91,000 94,000      
Complete WWTP Site Selection, etc. 541,000 563,000      
Vehicle & Equipment Storage Bldg. 487,000        
WR-3-1 Pipe Project 771,000        
WR-3-3 Pipe Project 957,000        
WR-6-1 Pipe Project 763,000        
WR-6-2 Pipe Project 207,000        
WR-6-3 Pipe Project   1,675,000      
Pump Station 8 project   225,000      
Anaerobic Digester Improvements   2,700,000      
6.9 MGD WWTP     5,499,000 5,719,000 54,536,000
Pump Station 27 Project     321,000    
Pump Station 16 Project     1,639,000    
WWTP Excess Flow Facility       1,095,000 5,315,000
Second Electrical Power Feed-WWTP       110,000 519,000
Flood Protectin & WWTP Site Fill       329,000 1,557,000
PS 25 Project       941,000  
YTC-2-2 Pipe Project         804,000
YTC-3-3 Pipe Project         881,000
FM/PS 25 Project         788,000
PS 28 Project         695,000
TOTAL $5,604,000 $7,114,000 $9,390,000 $10,203,000 $67,186,000