CHAPTER FIVE - SCHEDULES AND COST ESTIMATES
5.1 GENERAL
Proposed capital improvements and airside and landside maintenance at Lawrence Municipal Airport are scheduled for three successive time periods as follows:
Phase I 2001 - 2005
Phase II 2006 - 2010
Phase III 2011 - 2020
The following sections describe the various improvements, by phase, along with an estimated cost for each item. The development items are shown on the Airport Layout Plan (ALP) and/or the Terminal Area Plan (TAP) drawings. The recommended phasing is not absolute and changes in aviation demand or economics may alter the timing of the proposed development.
Estimates were developed using current (2000) costs. Each figure represents an estimate of the total project cost. The estimates include construction, engineering, administration, testing, surveying and legal expenses. Since these are preliminary estimates for planning purposes, a contingency amount was added to cover unforeseen problems that may occur during actual design. This approach reduces the likelihood of budget surprises when detailed design is completed. It should be noted, all estimates are "order of magnitude" only, and should be viewed as such. They should be reviewed and updated periodically, as necessary, to account for inflation, changes in the economy, future construction innovations and/or changes in local conditions.
5.2 PHASE I (2001-2005)
During this phase, several major development and reconstruction items are needed to maintain safe and efficient airport operations. The first major project proposed is the extension and strengthening of Runway 15-33. Further items include expansion and reconstruction of the aircraft parking apron; reconstruction of the parallel taxiway to Runway 15-33; construction of a parallel taxiway to Runway 1-19; expansion of the auto parking lot and installation of a city sewer line.
Miscellaneous items recommended for this phase include the installation of precision approach path indicators on all runway ends and runway end identifiers lights on runways 15, 1 and 19.
The remaining item, proposed for Phase I development, is the construction of executive/corporate and T-hangars, when and as needed.
The summary of Phase I improvement costs, as shown in Table 5-1, totals approximately $6.2 million. All development items, except hangar construction, auto parking and sewer line, would be eligible for 90 percent federal funding. The remaining 10 percent would be the local responsibility. Hangar construction would be funded by the City and/or by others from the private sector. The sewer line would be funded by the City.
|
TABLE 5-1PHASE I (2001-2005)
| |||
|
Development Item |
Federal |
Local |
Total |
|
Environmental Assessment for Runway Extension |
$67,500 |
$7,500 |
$75,000 |
|
Land Acquisition |
157,500 |
17,500 |
175,000 |
|
Extend Runway 15-33 500 feet to a length of 5,500 feet including Parallel Taxiway, Lighting and Signage
|
1,174,500 |
130,500 |
1,305,000 |
|
Rehabilitate and Strengthen Runway 15-33 to 60,000 Pounds |
540,000 |
60,000 |
600,000 |
|
Expand Apron and Reconstruct Existing Apron, Install Apron Flood Lighting
|
1,042,200 |
115,800 |
1,158,000 |
|
Expand Auto Parking |
0 |
300,000 |
300,000 |
|
Reconstruct Parallel Taxiway to Runway 15-33, 35 feet wide, Install new Taxiway Lighting and Signage
|
765,000 |
85,000 |
850,000 |
|
Construct Partial Parallel Taxiway from Taxiway A to Approach End of Runway 19, Install Taxiway Lighting and Signage
|
315,000 |
35,000 |
350,000 |
|
Install City Sewer Service
|
0 |
500,000 |
500,000 |
|
Construct Additional T-hangars and Construct Access Taxiways
|
90,000 |
210,000 |
300,000 |
|
Install PAPI-2 on Both Ends of Runway 1-19
|
72,000 |
8,000 |
80,000 |
|
Install REIL’s on Runway 33 and on Both Ends of Runway 1-19
|
67,500 |
7,500 |
75,000 |
|
Complete the Parallel Taxiway on Runway 1-19
|
360,000 |
40,000 |
400,000 |
|
PHASE I TOTAL |
$4,651,200 |
$1,516,800 |
$6,168,000 |
5.3 PHASE II (2006-2010)
This phase of airport development provides for continued airfield maintenance and runway and taxiway improvements. The primary runway would also be extended by 600 feet and the terminal would be upgraded. Also included in this phase is land acquisition and hangar construction.
Tabulation of Phase II development costs is presented in Table 5-2. The cost estimate totals approximately $7.2 million.
|
TABLE 5-2PHASE II (2006-2010) |
| |||||||
|
|
Development Item |
Federal |
Local |
Total | ||||
|
Improve Safety Area on Runway 15-33 |
$1,800,000 |
$200,000 |
$2,000,000 |
| ||||
|
Rehabilitate Lighting System on Runway 15-33
|
135,000 |
15,000 |
150,000 |
| ||||
|
Expand Aircraft Parking Apron |
900,000 |
100,000 |
1,000,000 |
| ||||
|
Upgrade the Terminal Building |
0 |
50,000 |
50,000 |
| ||||
|
Environmental Assessment for Runway Extension |
90,000 |
10,000 |
90,000 |
| ||||
|
Acquire Land |
225,000 |
25,000 |
250,000 |
| ||||
|
Extend Runway 15-33, 600 feet to South including Relocation of MALSR and Glide Slope |
900,000 |
100,000 |
1,000,000 |
| ||||
|
Widen airport Access Road |
0 |
150,000 |
150,000 |
| ||||
|
Construct Access Taxiways to Executive Hangars |
99,000 |
11,000 |
110,000 |
| ||||
|
Construct Executive Hangars |
|
|
By Others |
| ||||
|
Construct Access Taxiways to T-Hangars |
146,250 |
16,250 |
162,500 |
| ||||
|
Construct T-Hangars |
|
|
By Others |
| ||||
|
Expand Apron |
630,000 |
70,000 |
700,000 |
| ||||
|
Rehabilitate Airfield Pavements |
1,350,000 |
150,000 |
1,500,000 |
| ||||
|
PHASE II TOTAL |
$6,275,250 |
$897,250 |
$7,162,500 |
| ||||
5.4 PHASE III (2011-2020)
This phase of development consists primarily of rehabilitation of airfield pavements and construction of corporate and T-hangars.
The estimated costs for improvements in Phase III are approximately 2.3 million dollars, as shown in Table 5-3.
|
|
TABLE 5-3PHASE III (2011-2020) |
| ||||||||
|
Development Item |
Federal |
Local |
Total |
| ||||||
|
|
Airfield Pavement Rehabilitation |
$1,800,000 |
$200,000 |
$2,000,000 | ||||||
|
|
Executive Hangars |
|
|
By Others | ||||||
|
|
Construct Access Taxiways to Executive Hangars |
135,000 |
15,000 |
150,000 | ||||||
|
|
Construct T-Hangars |
|
|
By Others | ||||||
|
|
Construct Access Taxiways to T-Hangars |
157,500 |
17,500 |
175,000 | ||||||
|
|
PHASE III TOTAL |
$2,092,500 |
$232,500 |
$2,325,000 | ||||||
5.5 CAPITAL IMPROVEMENT PROGRAM (CIP)
The CIP differs from the initial five-year facility development recommendations, previously identified, on the basis of funding. The latter was based strictly on facility needs, assuming maximum funding availability. The CIP takes this analysis one step further. It identifies anticipated funds available for project development over the initial five years, thus matching projects that can be implemented given the funding availability.
Potential funds available for project development at Lawrence during the development period will include several sources. These sources include federal (FAA) discretionary funds, local and private funds. Table 5-4 presents the 2001-2005 (five-year) Capital Improvement Program for the Lawrence Municipal Airport, based on anticipated funding availability.
TABLE 5-42001-2005 CAPITAL IMPROVEMENT PROGRAM
| ||||
|
Year |
Development Item |
Federal |
Local |
Total |
|
2001 |
Environmental Assessment for Runway Extension |
$67,500 |
$7,500 |
$75,000 |
|
2001 |
Land Acquisition |
157,500 |
17,500 |
175,000 |
|
2001 |
Extend Runway 15-33 500 feet to a length of 5,500 feet including Parallel Taxiway, Lighting and Signage
|
1,174,500 |
130,500 |
1,305,000 |
|
2001 |
Rehabilitate and Strengthen Runway 15-33 to 60,000 Pounds |
540,000 |
60,000 |
600,000 |
|
2001 |
Expand Apron and Reconstruct Existing Apron, Install Apron Flood Lighting
|
1,042,200 |
115,800 |
1,158,000 |
|
2001 |
Expand Auto Parking |
0 |
300,000 |
300,000 |
|
2002 |
Reconstruct Parallel Taxiway to Runway 15-33, 35 feet wide, Install new Taxiway Lighting and Signage
|
765,000 |
85,000 |
850,000 |
|
2002 |
Construct Partial Parallel Taxiway from Taxiway A to Approach End of Runway 19, Install Taxiway Lighting and Signage
|
315,000 |
35,000 |
350,000 |
|
2002 |
Install City Sewer Service
|
0 |
500,000 |
500,000 |
|
2003 |
Construct Additional T-hangars and Construct Access Taxiways
|
90,000 |
210,000 |
300,000 |
|
2003 |
Install PAPI-2 on Both Ends of Runway 1-19
|
72,000 |
8,000 |
80,000 |
|
2004 |
Install REIL’s on Runway 33 and on Both Ends of Runway 1-19
|
67,500 |
7,500 |
75,000 |
|
2005 |
Complete the Parallel Taxiway on Runway 1-19
|
360,000 |
40,000 |
400,000 |
|
|
CIP TOTAL |
$4,651,200 |
$1,516,800 |
$6,168,000 |
5.6 SUMMARY
The phased 20-year development plan reflects needed airport facilities resulting from projected demand, system deficiencies, and facility aging. Availability of federal, state and local funding sources, private participation, and economic trends will affect the sequence and extent of development at the airport.
Table 5-5 presents a summary of total development costs for all phases of the 20-year planning period. Recommended improvements for the ultimate airport build-out are estimated to cost approximately $15.7 million.
|
TABLE 5-5TOTAL DEVELOPMENT COSTS | |
|
Phase |
Cost Estimate |
|
Phase I (2001-2005) |
$6,168,000 |
|
Phase II (2005-2010) |
7,162,500 |
|
Phase III (2011-2020) |
2,325,000 |
|
TOTAL |
$15,655,500 |
Care should be taken during implementation of the development items to combine projects and adjust to current needs to optimize the facility gained per expenditure and to maximize airport operational capabilities. Likewise, this plan should become a working tool to be updated as conditions change, i.e., funding sources, local economy, variation in aviation demand, etc.
A funding schedule for the phased development is presented in Table 5-6. This schedule presents the total cost for each phase and the funding levels for federal, and local participation. The average annual cost of the 20-year development plan for the Lawrence Municipal Airport is approximately $132,330, or $2,646,500 total.
|
TABLE 5-6FUNDING SCHEDULE
|
| ||||
|
|
Phase |
Total Cost |
FAA |
Local | |
|
|
Phase I (2001-2005) |
$6,168,000 |
$4,651,200 |
$1,516,800 | |
|
|
Phase II (2006-2010) |
7,162,500 |
6,275,250 |
897,250 | |
|
|
Phase III (2011-2020) |
2,325,000 |
2,092,500 |
||